Select the correct answer.
Which statement is true with regard to project scheduling?

A. Scheduling in plan-based processes does not change with the progress of the project.

B. Plan-based processes use an iterative approach for scheduling each phase of the project.

C. Scheduling in an agile process involves planning the short-term phases of a project.

D. Agile processes require less detail than plan-based processes do in an initial project schedule.

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 23.06.2019 15:00
Jake really works well with numbers and is skilled with computers but doesn't work well with others. which of the jobs discussed in this unit might be best for jake? why?
Answers: 3
question
Computers and Technology, 24.06.2019 01:00
The initial tableau of a linear programming problem is given. use the simplex method to solve it. x 1 x 2 x 3 s 1 s 2 z 1 2 4 1 0 0 8 3 4 1 0 1 0 10 minus3 minus12 1 0 0 1 0 the maximum is nothing when x 1equals nothing, x 2equals nothing, x 3equals nothing, s 1equals3, and s 2equals0. (be sure to simplify to lowest terms if necessary.)
Answers: 2
question
Computers and Technology, 24.06.2019 13:00
Your mom wants to purchase a laptop computer. she said she wants her new computer to be able to play her dvds so she can listen to music and wants to know what type of optical drives will play her disk. which type of drive should she look for?
Answers: 1
question
Computers and Technology, 24.06.2019 14:30
Alison is having a hard time at work because hee inbox is flooded with emails every day. some of these emails are unsolicited. some of other she don’t need. which action should she take to better manager her emails?
Answers: 1
You know the right answer?
Need answer ASAP. I’ll Mark brainliest

Select the correct answer.
Which statemen...
Questions