A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?

2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?

3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?

4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 21.06.2019 13:20
Raymond ozzie, the software designer who was critical in the development of lotus notes, was able to dictate the terms under which ibm acquired lotus. this illustrates that he had bargaining power based on the cost required by the firm to replace him.
Answers: 3
question
Computers and Technology, 21.06.2019 17:00
Ineed a good science fair name i’m doing a homemade water filter and i have no idea what the title should be plz
Answers: 1
question
Computers and Technology, 22.06.2019 11:10
Which are not examples of chronic or persistent stress? moving
Answers: 1
question
Computers and Technology, 23.06.2019 12:00
If you embed a word table into powerpoint, what happens when you make edits to the embedded data? a. edits made to embedded data change the data in the source file; however, edits made to the source file will not be reflected in the embedded data. b. edits made to embedded data will change the data in the source file, and edits made to the source file will be reflected in the embedded data. c. edits made to embedded data don't change the data in the source file, nor will edits made to the source file be reflected in the embedded data. d. edits made to embedded data don't change the data in the source file; however, edits made to the source file will be reflected in the embedded data.
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Mathematics, 05.12.2020 23:00
question
Chemistry, 05.12.2020 23:00
question
Biology, 05.12.2020 23:00
question
Mathematics, 05.12.2020 23:00
question
Mathematics, 05.12.2020 23:00