The critical path in a project network is: A. The Shortest path through the network. B. Longest path through the network. C. Network path with the most difficult activities. D. Network path using the most resources.

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 08:30
Today is the anniversary of me being on yet, i don't need it anymore! here's a picture of my dog wearing a bowtie! my question is, how do i delete my account?
Answers: 1
question
Computers and Technology, 22.06.2019 16:30
Primary tech skills are skills that are necessary for success in online education
Answers: 3
question
Computers and Technology, 23.06.2019 04:00
Laire writes a letter to her grandmother, in which she describes an amusement park she visited last week. she adds pictures of that place in her letter. which feature of a word processing program will claire to remove unwanted parts of the pictures?
Answers: 3
question
Computers and Technology, 23.06.2019 17:00
What are the 12 colors of the spectrum called?
Answers: 1
You know the right answer?
The critical path in a project network is: A. The Shortest path through the network. B. Longest path...
Questions
question
Mathematics, 22.06.2019 03:30
question
Social Studies, 22.06.2019 03:30