In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.

a. True.
b. False.

ansver
Answers: 1

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 05:20
Write a program called assignment3 (saved in a ļ¬le assignment3.java) that computes the greatest common divisor of two given integers. one of the oldest numerical algorithms was described by the greek mathematician, euclid, in 300 b.c. it is a simple but very eā†µective algorithm that computes the greatest common divisor of two given integers. for instance, given integers 24 and 18, the greatest common divisor is 6, because 6 is the largest integer that divides evenly into both 24 and 18. we will denote the greatest common divisor of x and y as gcd(x, y). the algorithm is based on the clever idea that the gcd(x, y) = gcd(x ! y, y) if x > = y and gcd(x, y) = gcd(x, y ! x) if x < y. the algorithm consists of a series of steps (loop iterations) where the ā€œlargerā€ integer is replaced by the diā†µerence of the larger and smaller integer. this continues until the two values are equal. that is then the gcd.
Answers: 3
question
Computers and Technology, 22.06.2019 09:40
In the lab, which of the following displayed a list of all installed services and included a description of the service, the current state, and whether the service started automatically or manually? a. the services manager b. the applications summary c. the recommended services d. list the safe services list
Answers: 2
question
Computers and Technology, 22.06.2019 10:20
Shown below is the start of a coding region within the fist exon of a gene. 5'--3' 3'--5' how many cas9 pam sequences are present?
Answers: 1
question
Computers and Technology, 23.06.2019 08:30
Based on your knowledge of a good network, describe what you think is a perfect network would be. what kind of information and resources could users share on this network. what would the network administrator do? what kind of communication would be used?
Answers: 1
You know the right answer?
In assigning a value for the most pessimistic (b) duration, the project manager should estimate the...
Questions
question
Mathematics, 01.12.2020 22:50
question
Social Studies, 01.12.2020 22:50
question
Mathematics, 01.12.2020 22:50
question
Mathematics, 01.12.2020 22:50