Which of these statements regarding time-cost tradeoffs in cpm networks is true?
a. crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
b. crashing is not possible unless there are multiple critical paths.
c. crashing a project often reduces the length of long-duration, but noncritical, activities.
d. the crash time always exceeds the normal time.
e. activities not on the critical path can never be on the critical path, even after crashing.

ansver
Answers: 1

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 16:20
It policy compliance and emerging technologies respond to the following: propose at least three control measures that organizations need to put in place to ensure that they remain complaint with emerging technologies and in a continually changing it environment. examine the correlation of effective configuration management and change control procedures to remain compliant with emerging technologies and it security changes.
Answers: 2
question
Computers and Technology, 22.06.2019 18:00
Budgets you to do all of the following expect a) send frivolously b) avoid over spending c) gain financial independence d) examine your priorities and goals
Answers: 2
question
Computers and Technology, 22.06.2019 20:00
What is the term for water wave that is created by an underwater earthquake
Answers: 1
question
Computers and Technology, 23.06.2019 03:30
In vista and windows 7, the appearance and personalization option allows you to change the
Answers: 1
You know the right answer?
Which of these statements regarding time-cost tradeoffs in cpm networks is true?
a. crashing...
Questions
question
Mathematics, 23.01.2021 05:00
question
Mathematics, 23.01.2021 05:00
question
Mathematics, 23.01.2021 05:00
question
Biology, 23.01.2021 05:00
question
English, 23.01.2021 05:00