In a pert network, non-critical activities that have little slack need to be monitored closely
a. because pert treats all activities as equally important
b. because near-critical paths could become critical paths with small delays in these activities
c. because slack is undesirable and needs to be eliminated
d. because they are causing the entire project to be delayed e. because they have a high risk of not being completed
Answers: 2
Computers and Technology, 22.06.2019 04:00
When you collaborate or meet with a person or group online, it is called
Answers: 1
Computers and Technology, 22.06.2019 21:30
Elements such as fonts colors visual structure graphics and the interface of a web page should complement each other to ensure blank
Answers: 3
Computers and Technology, 23.06.2019 17:30
Per the municipal solid waste report, what are the most common sources of waste (trash
Answers: 3
Computers and Technology, 25.06.2019 03:30
What best describes the purpose of occupational safety and health administration
Answers: 1
In a pert network, non-critical activities that have little slack need to be monitored closely
Chemistry, 06.12.2021 23:20
Spanish, 06.12.2021 23:20
Mathematics, 06.12.2021 23:20
English, 06.12.2021 23:20
Mathematics, 06.12.2021 23:20
Mathematics, 06.12.2021 23:20
Social Studies, 06.12.2021 23:20
Mathematics, 06.12.2021 23:20
Mathematics, 06.12.2021 23:20
Mathematics, 06.12.2021 23:20
Social Studies, 06.12.2021 23:20
Mathematics, 06.12.2021 23:20