Business, 20.10.2021 14:00 VoidedAngel

Earliest finish time (EF) is the earliest time by which a specific activity can be completed, calculated Question 37 options:___. a. by subtracting the activity’s estimated duration from the earliest finish time of the activity's predecessor: EF = EF predecessor - Estimated Duration.
b. by subtracting the activity’s estimated duration to the activity’s earliest start time: EF = ES - Estimated Duration.
c. by adding the activity’s estimated duration to the earliest start time of the activity's succeeding activity: EF = ES succeeding activity + Estimated Duration.
d. by adding the activity’s estimated duration to the activity’s earliest start time: EF = ES + Estimated Duration

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 16:30
Who got instagram! ? if you do give it to me
Answers: 1
question
Business, 22.06.2019 21:00
In a transportation minimization problem, the negative improvement index associated with a cell indicates that reallocating units to that cell would lower costs.truefalse
Answers: 1
question
Business, 23.06.2019 02:30
Complete electronics inc. sells a point-of-sale computer with a two-year service contract. complete collects $ 2 comma 500 cash for the selling price of the computer and $ 576 for the two-year service contract. how is revenue recognized?
Answers: 2
question
Business, 23.06.2019 07:50
If a price increase from $5 to $7 causes quantity demanded to fall from 150 to 100 and vice-versa, what is the absolute value of the own price elasticity at a price of $7? note that the question is about the price point of $7, and not $5.
Answers: 2
You know the right answer?
Earliest finish time (EF) is the earliest time by which a specific activity can be completed, calcul...
Questions
question
History, 13.11.2019 16:31