Business, 24.08.2021 15:50 lexigarwood
Each of two mutually exclusive projects involves an investment of $168,000. Net cash flows for the projects are as follows:
Year Project "A" Project "B"
1. $60,000 $55,000
2. 68,000 64,000
3. 36,000 42,000
Required:
a. Calculate each project's payback period.
b. Compute the Net Present Value (NPV) of each project when the firm's cost of capital is 8 percent.
c. Internal Rate of Return (IRR) -Your choice; based on your answer to part (B).
d. Modified Internal Rate of Return (MIRR) Your choice; based on your answer to part (B).
Answers: 3
Business, 21.06.2019 20:30
The link between volume of production and the cost of building manufacturing operations is particularly important in industries characterized byanswers: process innovations.product manufacturing.product innovation.process manufacturing.
Answers: 1
Business, 22.06.2019 07:30
When selecting a savings account, you should look at the following factors except annual percentage yield (apy) fees minimum balance interest thresholds taxes paid on the interest variable interest rates
Answers: 1
Business, 22.06.2019 11:10
Wilson company paid $5,000 for a 4-month insurance premium in advance on november 1, with coverage beginning on that date. the balance in the prepaid insurance account before adjustment at the end of the year is $5,000, and no adjustments had been made previously. the adjusting entry required on december 31 is: (a) debit cash. $5,000: credit prepaid insurance. $5,000. (b) debit prepaid insurance. $2,500: credit insurance expense. $2500. (c) debit prepaid insurance. $1250: credit insurance expense. $1250. (d) debit insurance expense. $1250: credit prepaid insurance. $1250. (e) debit insurance expense. $2500: credit prepaid insurance. $2500.
Answers: 1
Business, 22.06.2019 11:40
Zachary company produces commercial gardening equipment. since production is highly automated, the company allocates its overhead costs to product lines using activity-based costing. the costs and cost drivers associated with the four overhead activity cost pools follow: activities unit level batch level product level facility level cost $ 64,800 $ 27,730 $ 15,000 $ 154,000 cost driver 2,400 labor hrs. 47 setups percentage of use 11,000 units production of 780 sets of cutting shears, one of the companyâs 20 products, took 240 labor hours and 7 setups and consumed 15 percent of the product-sustaining activities. required: (a) had the company used labor hours as a company wide allocation base, how much overhead would it have allocated to the cutting shears? (b) how much overhead is allocated to the cutting shears using activity-based costing? (c) compute the overhead cost per unit for cutting shears first using activity-based costing and then using direct labor hours for allocation if 780 units are produced. if direct product costs are $150 and the product is priced at 30 percent above cost for what price would the product sell under each allocation system? (d) assuming that activity-based costing provides a more accurate estimate of cost, indicate whether the cutting shears would be over- or underpriced if direct labor hours are used as an allocation base. explain how over-or undercosting can affect vaulker's profitability. (e) comment on the validity of using the allocated facility-level cost in the pricing decision. should other costs be considered in a cost- plus pricing decision? if so, which ones? what costs would you include if you were trying to decide whether to accept a special order?
Answers: 1
Each of two mutually exclusive projects involves an investment of $168,000. Net cash flows for the p...
Mathematics, 05.11.2020 07:10
SAT, 05.11.2020 07:10
Mathematics, 05.11.2020 07:10
Mathematics, 05.11.2020 07:10
Chemistry, 05.11.2020 07:10
Law, 05.11.2020 07:10
Mathematics, 05.11.2020 07:10
History, 05.11.2020 07:10
Physics, 05.11.2020 07:10
Mathematics, 05.11.2020 07:10
Geography, 05.11.2020 07:10
Chemistry, 05.11.2020 07:10
Chemistry, 05.11.2020 07:10
Spanish, 05.11.2020 07:10