A project leader has realized that two activities in the project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will the project leader decide which activity should be scheduled first? a. The activity with the most slack
b. The activity with the least slack
c. The activity with the smallest duration
d. The activity with the lowest identification number
e. The activity with the highest cost

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 21:30
An office manager is concerned with declining productivity. despite the fact that she regularly monitors her clerical staff four times each day—at 9: 00 am, 11: 00 am, 1: 00 pm, and again at 3: 00 pm—office productivity has declined 30 percent since she assumed the helm one year ago. would you recommend that the office manager invest more time monitoring the productivity of her clerical staff? explain.
Answers: 3
question
Business, 22.06.2019 05:30
In most states, a licensee must provide a(n) of any existing agency relationships to all parties
Answers: 3
question
Business, 22.06.2019 12:30
On june 1, 2017, blossom company was started with an initial investment in the company of $22,360 cash. here are the assets, liabilities, and common stock of the company at june 30, 2017, and the revenues and expenses for the month of june, its first month of operations: cash $4,960 notes payable $12,720 accounts receivable 4,340 accounts payable 840 service revenue 7,860 supplies expense 1,100 supplies 2,300 maintenance and repairs expense 700 advertising expense 400 utilities expense 200 equipment 26,360 salaries and wages expense 1,760 common stock 22,360 in june, the company issued no additional stock but paid dividends of $1,660. prepare an income statement for the month of june.
Answers: 3
question
Business, 22.06.2019 14:20
Anew 2-lane road is needed in a part of town that is growing. at some point the road will need 4 lanes to handle the anticipated traffic. if the city's optimistic estimate of growth is used, the expansion will be needed in 4 years and has a probability of happening of 40%. for the most likely and pessimistic estimates, the expansion will be needed in 8 and 15 years respectively. the probability of the pessimistic estimate happening is 20%. the expansion will cost $ 4.2 million and the interest rate is 8%. what is the expected pw the expansion will cost?
Answers: 1
You know the right answer?
A project leader has realized that two activities in the project cannot be done at the same time bec...
Questions
question
Mathematics, 20.02.2020 03:40
question
Mathematics, 20.02.2020 03:41