The actual and budgeted costs for Synergy Inc.'s actual level of activity are as follows: Actual Costs Budgeted Costs
Units produced 1,500 1,500
Direct materials cost $5,630 $5,560
Direct labor cost 1,600 1,540
VOH:
Maintenance 735 640
Power 270 200
FOH:
Grounds keeping 1,450 1,400
Depreciation 500 500
Calculate the flexible budget variance.
a. $295U
b. $70F
c. $50F
d. $345U

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 16:10
(4 points) suppose the production function in the solow model is given by yt = ak¯ 3/4 t l 1/4 t . (a) what are the five equations and five unknowns that summarize the solow model? (b) show the transition dynamics in the solow model if ¯sy0 < ¯dk0. make sure you label the axes, curves, initial level of capital and steady-state level of capital. (c) solve for capital, output, capital per person, and output per person in the steady state. (d) if a¯ = 2, l¯ = 4, ¯s = 0.2, and ¯d = 0.05, calculate the steady-state level of capital and output per person.
Answers: 3
question
Business, 22.06.2019 20:00
Which of the following statements is true of the balanced-scorecard? a. it is a more or less a one-dimensional metric of measuring competitive advantages of a firm. b. it is one of the traditional approaches of measuring firm performance. c. its primary focus is to base a firm's strategic goals entirely on external performance dimensions. d. it attempts to provide a holistic perspective on firm performance.
Answers: 1
question
Business, 22.06.2019 20:00
Double corporation acquired all of the common stock of simple company for
Answers: 1
question
Business, 22.06.2019 21:00
Noah met an old friend at a coffee shop. he jotted down the friend's new phone number, but later that afternoon he could not find it or remember what he had done with it. a couple of days later, noah went back to the coffee shop, and while waiting in line, he suddenly remembered where he had put the phone number. this is an example of:
Answers: 1
You know the right answer?
The actual and budgeted costs for Synergy Inc.'s actual level of activity are as follows: Actual Co...
Questions