A dependency requiring a design be completed before manufacturing can start is an example of a(n): A. Discretionary Dependency.
B. External dependency.
C. Mandatory dependency.
D. Scope dependency.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 07:30
Jordan, inc. sells fireworks. the company’s marketing director developed the following cost of goods sold budget for april, may, june, and july. april may june july budgeted cost of goods sold $62,000 $72,000 $82,000 $88,000 jordan had a beginning inventory balance of $3,000 on april 1 and a beginning balance in accounts payable of $14,600. the company desires to maintain an ending inventory balance equal to 15 percent of the next period’s cost of goods sold. jordan makes all purchases on account. the company pays 65 percent of accounts payable in the month of purchase and the remaining 35 percent in the month following purchase. required prepare an inventory purchases budget for april, may, and june. determine the amount of ending inventory jordan will report on the end-of-quarter pro forma balance sheet. prepare a schedule of cash payments for inventory for april, may, and june. determine the balance in accounts payable jordan will report on the end-of-quarter pro forma balance sheet.
Answers: 2
question
Business, 22.06.2019 09:30
Oliver's company is planning the launch of their hybrid cars. the company has included "never-before-seen" product benefits in the hybrid cars. which type of advertising should oliver's company use for the new cars?
Answers: 1
question
Business, 22.06.2019 11:30
Amano s preguntes cationing to come fonds and consumer good 8. why did the u.s. government use rationing for some foods and consumer goods during world war ii?
Answers: 1
question
Business, 22.06.2019 20:30
Afirm wants to hire a project manager (pm) at a salary of $100,000. 30% of pms have high ability, and 70% of pms have low ability. high ability pms generate $120,000 in revenue and low ability pms generate $80,000 in revenue. in addition to differences in productivity, high and low ability pms have different outside offers. if a high ability pm is not hired by the firm, she can work for another company at a salary of $80,000. if the low ability pm is not hired by the firm, she can work for another company for $70,000. high ability pms are also able to get a project management professional (pmp) certification at a cost of $1,000. low ability pms are unable to get a pmp certification (they would fail the test). the firm is not able to observe a pm’s ability, but is able to observe and verify whether or not the pm has a pmp certificate.(a) draw the extensive form of the game.expert answer
Answers: 3
You know the right answer?
A dependency requiring a design be completed before manufacturing can start is an example of a(n):...
Questions
question
Mathematics, 25.08.2019 22:30
question
Engineering, 25.08.2019 22:30