When using the Time-Cost Critical Path Method (CPM) Scheduling Model to "crash" a project, you know when you have arrived at the optimal solution when . a) You have found the critical path
b) You have run out of crash time
c) You no longer have a linear relationship with costs
d) You have reached the minimum total cost
e) You have run out of crash costs

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 16:00
Jodi is trying to save money for a down payment on a house. she invests $6,000 into an account paying 5.5% simple interest. for how long must she save if she needs $7,300 for the down payment? a. 2 years b. 3 years c. 4 years d. 5 years
Answers: 1
question
Business, 22.06.2019 05:10
The total value of your portfolio is $10,000: $3,000 of it is invested in stock a and the remainder invested in stock b. stock a has a beta of 0.8; stock b has a beta of 1.2. the risk premium on the market portfolio is 8%; the risk-free rate is 2%. additional information on stocks a and b is provided below. return in each state state probability of state stock a stock b excellent 15% 15% 5% normal 50% 9% 7% poor 35% -15% 10% what are each stock’s expected return and the standard deviation? what are the expected return and the standard deviation of your portfolio? what is the beta of your portfolio? using capm, what is the expected return on the portfolio? given your answer above, would you buy, sell, or hold the portfolio?
Answers: 1
question
Business, 22.06.2019 14:30
Stella company sells only two products, product a and product b. product a product b total selling price $50 $30 variable cost per unit $20 $10 total fixed costs $2,110,000 stella sells two units of product a for each unit it sells of product b. stella faces a tax rate of 40%. stella desires a net afterminustax income of $54,000. the breakeven point in units would be
Answers: 3
question
Business, 22.06.2019 14:30
What’s the present value of a perpetuity that pays $250 per year if the appropriate interest rate is 5%? $4,750 $5,000 $5,250 $5,513 $5,788what is the present value of the following cash flow stream at a rate of 8.0%, rounded to the nearest dollar? cash flows: today (t = 0) it is $750, after one year (t = 1) it is $2,450, at t = 2 it is $3,175, and at t=3 it is $4,400. draw a time line. $7,917 $8,333 $8,772 $9,233 $9,695
Answers: 2
You know the right answer?
When using the Time-Cost Critical Path Method (CPM) Scheduling Model to "crash" a project, you know...
Questions
question
Mathematics, 12.02.2021 17:00
question
Mathematics, 12.02.2021 17:00
question
Mathematics, 12.02.2021 17:00