On March 15, 2017, Gilbert Construction contracted to build a shopping center at a contract price of $220 million. The schedule of expected (which equals actual) cash collections and contract costs follows: Year Cash Collections Cost Incurred
2017 55 million $36 million
2018 88 million 81 million
2019 77 million 63 million
Total $220 million $180 million

Required:
a. Calculate the amount of revenue, expense, and net income for each of the three years 2017 through 2019, and for all three years combined, using the cost-to-cost revenue recognition method.
b. Discuss whether or not the cost-to-cost method provides a good measure of this construction com- pany's performance under the contract.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 14:30
Do savings and loan associations offer checking accounts?
Answers: 1
question
Business, 21.06.2019 16:00
Corey is trying to save money to buy a new tv. he invests $800 into an account paying 6.5% simple interest. for how long must he save if the tv costs $950? a. 2 years b. 3 years c. 4 years d. 5 years
Answers: 1
question
Business, 21.06.2019 16:10
Visburg concrete company pours concrete slabs for single-family dwellings. lancing construction company, which operates outside visburg's normal sales territory, asks visburg to pour 40 slabs for lancing's new development of homes. visburg has the capacity to build 300 slabs and is presently working on 250 of them. lancing is willing to pay only $3, 300 per slab. visburg estimates the cost of a typical job to include unit-level materials, $1, 440: unit-level labor, $720: and an allocated portion of facility-level overhead, $1, 200. required calculate the contribution to profit from the special order. should visburg accept or reject the special order to pour 40 slabs for $3, 300 each?
Answers: 2
question
Business, 22.06.2019 05:00
What is free trade? a. trade that is not subject to taxes or fees b. trade that governments do not interfere with c. trade with a high level of government regulation d. trade between states in the u.s. b
Answers: 1
You know the right answer?
On March 15, 2017, Gilbert Construction contracted to build a shopping center at a contract price of...
Questions
question
History, 11.07.2019 09:00
question
History, 11.07.2019 09:00
question
Mathematics, 11.07.2019 09:00
question
Mathematics, 11.07.2019 09:00
question
Biology, 11.07.2019 09:00