The following tasks must be performed on an assembly line in the sequence and times specified in order to make the XJP robot. Currently, & productive hours are available each day for production and the daily demand is 360 robots. Task Task time (sec.) Tasks that must precede
A 50
B 40
C 30 A
D 45 C

Required:
a. What is the percentage of idle time?
b. What is the efficiency of the line?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 10:10
An investment offers a total return of 18 percent over the coming year. janice yellen thinks the total real return on this investment will be only 14 percent. what does janice believe the inflation rate will be over the next year?
Answers: 3
question
Business, 22.06.2019 11:00
What is the advantage of developing criteria for assessing the effectiveness of business products and processes? a. assessment criteria are answers. b.assessment criteria are inexpensive. c.assessment criteria provide you with a list of relevant things to measure. d.assessment criteria provide you with a list of people to contact to learn more about process mentoring.
Answers: 3
question
Business, 22.06.2019 18:30
Hilary works at klothes kloset. she quickly the customers, and her cash drawer is always correct at the end of her shift. however, she never tries to "upsell" the customers (for example, by asking if they would like to purchase earrings to go with the shirt they chose or by suggesting a purse that matches the shoes they are buying). give hilary some constructive feedback on her performance.
Answers: 3
question
Business, 22.06.2019 19:30
The owner of firewood to go is considering buying a hydraulic wood splitter which sells for $50,000. he figures it will cost an additional $100 per cord to purchase and split wood with this machine, while he can sell each cord of split wood for $125. if, for this machine, design capacity is 50 cords per day, effective capacity is 40 cords per day, and actual output is expected to be 32 cords per day, what would be its efficiency?
Answers: 1
You know the right answer?
The following tasks must be performed on an assembly line in the sequence and times specified in ord...
Questions