Question 1 Accounting for Construction Contracts 10 Marks XYZ Ltd signs a contract on 30 June 2015, agreeing to build a bridge for ABC Limited at a
contract price of $40 million. XYZ Ltd estimates that construction costs will be as follows:

Year Ending Cost

30 June 2016 $10 000 000
30 June 2017 $16 000 000
30 June 2018 $ 6 000 000
$32 000 000
The contract provides that ABC will make payments on 30 June of each year as follows:
2016 $8 000 000
2017 $20 000 000
2018 $12 000 000
$40 000 000
XYZ now estimates at the beginning of the 2017 financial year that construction costs will be
as follows:

Year Ending Cost

30 June 2016 $10 000 000
30 June 2017 $21 000 000
30 June 2018 $15 000 000
$46 000 000
Required:
Calculate:
a) Percentage of completion for each of the three years. (4 marks)
b) Revenue to be recognised in each of the three years. (3 marks)
c) Gross profit/loss to be recognised in each of the three years. (3 marks)

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 03:00
What is the relationship between marginal external cost, marginal social cost, and marginal private cost? a. marginal social cost equals marginal private cost plus marginal external cost. b. marginal private cost plus marginal social cost equals marginal external cost. c. marginal social cost plus marginal external cost equals marginal private cost. d. marginal external cost equals marginal private cost minus marginal social cost. marginal external cost a. is expressed in dollars, so it is not an opportunity cost b. is an opportunity cost borne by someone other than the producer c. is equal to two times the marginal private cost d. is a convenient economics concept that is not real
Answers: 3
question
Business, 22.06.2019 04:30
Required prepare the necessary adjusting entries in the general journal as of december 31, assuming the following: on september 1, the company entered into a prepaid equipment maintenance contract. birch company paid $3,400 to cover maintenance service for six months, beginning september 1. the payment was debited to prepaid maintenance. supplies on hand at december 31 are $3,900. unearned commission fees at december 31 are $7,000. commission fees earned but not yet billed at december 31 are $3,500. (note: debit fees receivable.) birch company's lease calls for rent of $1,600 per month payable on the first of each month, plus an annual amount equal to 1% of annual commissions earned. this additional rent is payable on january 10 of the following year. (note: be sure to use the adjusted amount of commissions earned in computing the additional rent.)
Answers: 1
question
Business, 22.06.2019 07:30
1  2  3  4  5  6  7  8  9  10time remaining59: 30in  the dark game, how does the author develop the central idea that elizabeth van lew was a spymaster during the civil war? 1 2 3 4 5 6 7 8 9 10time remaining59: 30in the dark game, how does the author develop the central idea that elizabeth van lew was a spymaster during the civil war?
Answers: 1
question
Business, 22.06.2019 11:30
4.     chef a says that broth should be brought to a boil. chef b says that broth should be kept at an even, gentle simmer. which chef is correct? a. neither chef is correct. b. chef a is correct. c. both chefs are correct. d. chef b is correct. student c   incorrect which is right answer
Answers: 2
You know the right answer?
Question 1 Accounting for Construction Contracts 10 Marks XYZ Ltd signs a contract on 30 June 2015,...
Questions
question
Mathematics, 20.08.2019 15:30
question
Social Studies, 20.08.2019 15:30