Down Under Boomerang, Inc., is considering a new 3-year expansion project that requires an initial fixed asset investment of $2.33 million. The fixed asset falls into the 3-year MACRS class (MACRS schedule). The project is estimated to generate $1,735,000 in annual sales, with costs of $640,000. The project requires an initial investment in net working capital of $300,000, and the fixed asset will have a market value of $255,000 at the end of the project. Required:
a. If the tax rate is 25 percent, what is the project’s Year 0 net cash flow? Year 1? Year 2? Year 3?
b. If the required return is 9 percent, what is the project's NPV?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 20:30
(30 total points) suppose a firm’s production function is given by q = l1/2*k1/2. the marginal product of labor and the marginal product of capital are given by: mpl = 1/ 2 1/ 2 2l k , and mpk = 1/ 2 1/ 2 2k l . a) (12 points) if the price of labor is w = 48, and the price of capital is r = 12, how much labor and capital should the firm hire in order to minimize the cost of production if the firm wants to produce output q = 18?
Answers: 1
question
Business, 22.06.2019 20:30
Considered alone, which of the following would increase a company's current ratio? a. an increase in net fixed assets.b. an increase in accrued liabilities.c. an increase in notes payable.d. an increase in accounts receivable.e. an increase in accounts payable.
Answers: 3
question
Business, 22.06.2019 22:00
Exercise 2-12 cost behavior; high-low method [lo2-3, lo2-4] speedy parcel service operates a fleet of delivery trucks in a large metropolitan area. a careful study by the company’s cost analyst has determined that if a truck is driven 120,000 miles during a year, the average operating cost is 11.6 cents per mile. if a truck is driven only 80,000 miles during a year, the average operating cost increases to 13.6 cents per mile. required: 1.& 2. using the high-low method, estimate the variable and fixed cost elements of the annual cost of truck operation. (round the "variable cost per mile" to 3 decimal places.)
Answers: 3
question
Business, 22.06.2019 23:00
Which of the following is not one of the four principles of bottleneck management? a. increasing capacity at non-bottleneck stations is a mirageb. lost time at the bottleneck is lost system capacity.c. release work orders to the system at the bottleneck's capacity pace.d. increased bottleneck capacity is increased system capacity.e. bottlenecks should be moved to the end of the system process.
Answers: 1
You know the right answer?
Down Under Boomerang, Inc., is considering a new 3-year expansion project that requires an initial f...
Questions
question
Mathematics, 17.07.2021 18:50
question
Physics, 17.07.2021 18:50
question
English, 17.07.2021 18:50