A company is making plans for a new factory. One department has been allocated 12 semiautomatic machines. A small number (yet to be determined) of operators will be hired to provide the machines the needed occasional servicing (loading, unloading, adjusting, setup, and so no). A decision now needs to be made on how to organize the operators to do this. Three alternatives are being considered: 1. Assign each operator to his or her own machines.
2. Pool the operators so that any idle operator can take the next machine that needs servicing.
3. Combine the operators into a single crew that will work together on any machine needing servicing.

The running time (time between completing service on a machine and its requiring service again) of each machine is expected to have an exponential distribution, with a mean of 150 minutes. The service time is expected to have an exponential distribution, with a mean of 15 minutes for Alternatives 1 and 2, and 15 minutes divided by the number of operators for Alternative 3.

For the department to achieve the required production rate, there must be an average of at least 10 machines running at any time.

1. Suppose that Alternative 1 is used with a total of 3 operators (4 machines per operator), on average how many machines are down (either being serviced or waiting for service)? On average how many machines are running?
2. For Alternative 1, what is the maximum number of machines that can be assigned to a single operator while still achieving the required production rate?
3. What is the minimum number of operators needed to achieve the required production rate with Alternative 2?
4. For Alternative 3, what is the minimum size of the crew needed to achieve the required production rate?
5. Which Alternative maximizes the amount of time that all 12 machines are running?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 22:50
The winston company estimates that the factory overhead for the following year will be $1,250,000. the company has decided that the basis for applying factory overhead should be machine hours, which is estimated to be 50,000 hours. the total machine hours for the year were 54,300. the actual factory overhead for the year were $1,375,000. determine the over- or underapplied amount for the year.
Answers: 1
question
Business, 22.06.2019 07:20
Richardson hired j.c. flood company, a plumbing contractor, to correct a stoppage in the sewer line of her house. the plumbing company's 'snake' device, used to clear the line leading to the main sewer, became caught in the underground line. to release it, the company excavated a portion of the sewer line in richardson's backyard. in the process, the company discovered numerous leaks in a rusty, defective water pipe that ran parallel with the sewer line. to meet public regulations, the water pipe, of a type no longer approved for such service, had to be replaced either then or later, when the yard would have to be excavated again. the plumbing company proceeded to repair the water pipe. though richardson inspected the company's work daily and did not express any objection to the extra work involved in replacing the water pipe, she refused to pay any part of the total bill after the company completed the entire operation. j.c. flood company then sued richardson for the costs of labor and material it had furnished. (c) for what, if anything, should richardson be liable? explain."
Answers: 1
question
Business, 22.06.2019 11:10
Use the information below to answer the following question. the boxwood company sells blankets for $60 each. the following was taken from the inventory records during may. the company had no beginning inventory on may 1. date blankets units cost may 3 purchase 5 $20 10 sale 3 17 purchase 10 $24 20 sale 6 23 sale 3 30 purchase 10 $30 assuming that the company uses the perpetual inventory system, determine the gross profit for the month of may using the lifo cost method.
Answers: 1
question
Business, 22.06.2019 20:30
What talent or skill do u wish too develop for yourself
Answers: 1
You know the right answer?
A company is making plans for a new factory. One department has been allocated 12 semiautomatic mach...
Questions
question
Mathematics, 11.03.2021 20:30
question
Mathematics, 11.03.2021 20:30
question
Biology, 11.03.2021 20:30
question
Physics, 11.03.2021 20:30