Business, 04.04.2021 18:10 BigDaddy1220

A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 261, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However,
due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires
task A to be completed. To start task and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F
needs both task D and task Eto be completed. Finally, task G can start only once task Fis completed.
Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, What will the
estimated idle time in minutes for FOURTH workstation?
O a. 1.85
O b. 0.06
Oc 0.09
O d. None is the correct answer
O e 1.00

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 00:00
Which statement is true of both presidential and parliamentary systems of government? a. the executive branch operates independently from the legislative branch. b. the members of the legislative branch are directly elected by the people. c. the head of government is chosen by members of his or her political party. d. the head of government is directly elected by the people
Answers: 1
question
Business, 22.06.2019 16:40
Determine the hrm’s role in the performance management process and explain how to ensure the process aligns with the organization’s strategic plan.
Answers: 1
question
Business, 22.06.2019 20:50
Happy foods and general grains both produce similar puffed rice breakfast cereals. for both companies, thecost of producing a box of cereal is 45 cents, and it is not possible for either company to lower their productioncosts any further. how can one company achieve a competitive advantage over the other?
Answers: 1
question
Business, 23.06.2019 00:30
Emerson has an associate degree based on the chart below how will his employment opportunities change from 2008 to 2018
Answers: 3
You know the right answer?
A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy tha...