Business, 18.03.2021 01:10 PrincesaChrissy6366

End item P is composed of three subassemblies: K, L, and W. K is assembled using 3 Gs and 4 Hs; L is made of 2 Ms and 2 Ns; and W is made of 3 Zs. On-hand inventories are 20 Ls, 40 Gs, and 200 Hs. Scheduled receipts are 10 Ks at the start of week 3, 30 Ks at the start of week 6, and 200 Ws at the start of week 3. One hundred Ps will be shipped at the start of week 6, and another 100 at the start of week 7. Lead times are two weeks for subassemblies and one week for components G, H, and M. Final assembly of P requires one week. Include an extra 10 percent scrap allowance in each planned order of G. The minimum order size for H is 200 units. Develop each of the following:

a. A product structure tree.
b. A master schedule for P.
c. A material requirements plan for K, G, and H using lot-for-lot ordering.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 00:30
Norton manufacturing expects to produce 2,900 units in january and 3,600 units in february. norton budgets $20 per unit for direct materials. indirect materials are insignificant and not considered for budgeting purposes. the balance in the raw materials inventory account (all direct materials) on january 1 is $38,650. norton desires the ending balance in raw materials inventory to be 10% of the next month's direct materials needed for production. desired ending balance for february is $51,100. what is the cost of budgeted purchases of direct materials needed for january? $58,000 $65,200 $26,550 $25,150
Answers: 1
question
Business, 22.06.2019 02:30
Based on the supply and demand theory, why do medical doctors earn higher wages than child-care workers?
Answers: 1
question
Business, 22.06.2019 10:20
Sye chase started and operated a small family architectural firm in 2016. the firm was affected by two events: (1) chase provided $25,000 of services on account, and (2) he purchased $2,800 of supplies on account. there were $250 of supplies on hand as of december 31, 2016. record the two transactions in the accounts. record the required year-end adjusting entry to reflect the use of supplies and the required closing entries. post the entries in the t-accounts and prepare a post-closing trial balance.
Answers: 1
question
Business, 22.06.2019 14:10
When paul oā€™neill joined alcoa as ceo, he set a , that there would be zero workplace accidents. a lot of people in the organization thought this was impossible given how dangerous some aluminum-manufacturing jobs are, but alcoaā€™s safety record improved tremendously. as the board of governors of the american red cross considers planning, one option is to make strategic plans and then direct managers to align tactical and operational plans accordingly. another option is to have planning specialists managers across the organization make their own plans. why might this organizationā€™s executives opt for the latter approach? check all that apply. (a) the environment is a dynamic one, and department and frontline managers can come up with more responsive plans than can central leadership. (b)resources will be better coordinated across the organization in support of the overall strategy.(c) senior leadership will have more control over the organizationā€™s direction. (d)when managers come up with their own plans, they are likely to be more committed to following through on them.
Answers: 2
You know the right answer?
End item P is composed of three subassemblies: K, L, and W. K is assembled using 3 Gs and 4 Hs; L is...