Business, 09.03.2021 02:20 izzxizzy

A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the schedule performance index for the project

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 02:30
Atax on the sellers of coffee will a. increase the price of coffee paid by buyers, increase the effective price of coffee received by sellers, and increase the equilibrium quantity of coffee. b. increase the price of coffee paid by buyers, increase the e ffective price of coffee received by sellers, and decrease the equilibrium quantity of coffee. c. increase the price of coffee paid by buyers, decrease the effective price of coffee received by sellers, and increase the equilibrium quantity of coffee. d. increa se the price of coffee paid by buyers, decrease the effective price of coffee received by sellers, and decrease the equilibrium quantity of coffee.
Answers: 3
question
Business, 22.06.2019 13:30
1. is the act of declaring a drivers license void and terminated when it is determined that the license was issued through error or fraud.
Answers: 2
question
Business, 22.06.2019 19:40
Moody corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. at the beginning of the year, the company made the following estimates: machine-hours required to support estimated production 100,000 fixed manufacturing overhead cost $ 650,000 variable manufacturing overhead cost per machine-hour $ 3.00 required: 1. compute the plantwide predetermined overhead rate. 2. during the year, job 400 was started and completed. the following information was available with respect to this job: direct materials $ 450 direct labor cost $ 210 machine-hours used 40
Answers: 3
question
Business, 22.06.2019 21:20
Which of the following best explains why large companies pay less for goods from wholesalers? a. large companies are able to pay for the goods they purchase in cash. b. large companies are able to increase the efficiency of wholesale production. c. large companies can buy all or most of a wholesaler's stock. d. large companies have better-paid employees who are better negotiators.
Answers: 2
You know the right answer?
A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K,...
Questions
question
Health, 16.12.2021 01:20
question
English, 16.12.2021 01:20
question
English, 16.12.2021 01:20
question
Chemistry, 16.12.2021 01:20
question
Mathematics, 16.12.2021 01:20