Your project to obtain charitable donations is now 34 days into a planned 44-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 28 days of the project and to bring in $25,500. Even though we are 34 days into the project, we still see that we have only 92% of this activity complete. The second activity relates to company donations and is scheduled to run for 34 days starting on day 6 and extending through day 40. We estimate that, even though we should have (28/34) 82.35% of this activity complete, it is actually only 50 percent complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far, $175,000 has actually been brought in on the project. Required:
Calculate the Schedule Variance, Schedule Performance Index, and Cost (actually value in this case) Performance Index. How is the project going?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 14:50
Calvin works at a facility which processes apples. it costs the facility $0.68 to make either a jar of applesauce or a bottle of apple juice. due to the nature of the process and contractual agreements, calvin's facility must make and sell three jars of applesauce for every two bottles of apple juice. a jar of applesauce sells for $2.20, and a bottle of apple juice sells for $3.15. if the facility has annual overhead costs of $368,500, not including production costs, how many bottles of apple juice will the facility have sold when it breaks even every year? round to the nearest whole bottle, if necessary.
Answers: 3
question
Business, 22.06.2019 14:30
The face of a company is often that of the lowest paid employees who meet the customers. select one: true false
Answers: 1
question
Business, 22.06.2019 19:10
You have just been hired as a brand manager at kelsey-white, an american multinational consumer goods company. recently the firm invested in the development of k-w vision, a series of systems and processes that allow the use of up-to-date data and advanced analytics to drive informed decision making about k-w brands. it is 2018. the system is populated with 3 years of historical data. as brand manager for k-w’s blue laundry detergent, you are tasked to lead the brand's turnaround. use the vision platform to to develop your strategy and grow blue’s market share over the next 4 years.
Answers: 2
question
Business, 22.06.2019 19:20
Although appealing to more refined tastes, art as a collectible has not always performed so profitably. during 2003, an auction house sold a sculpture at auction for a price of $10,211,500. unfortunately for the previous owner, he had purchased it in 2000 at a price of $12,177,500. what was his annual rate of return on this sculpture? (a negative answer should be indicated by a minus sign. do not round intermediate calculations and enter your answer as
Answers: 2
You know the right answer?
Your project to obtain charitable donations is now 34 days into a planned 44-day project. The projec...
Questions
question
Biology, 26.01.2022 16:40
question
Mathematics, 26.01.2022 16:50