Martinez Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $594,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period: 2017 2018 2019
Costs to date $255,420 $433,620 $604,000
Estimated costs to 338,580 160,380 0
Progress billings to ate 271,000 547,000 901,000
Cash collected to date 241,000 497,000 901,000

Required:
a. Using the method, compute the estimated gross profit that would be recognized during each year of construction period.
b. Using the completed - contract method, compute the estimated gross profit that be recognized during each year of the period.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 08:30
What has caroline's payment history been like? support your answer with two examples
Answers: 3
question
Business, 22.06.2019 11:30
Which of the following is not an example of one of the four mail advantages of prices on a free market economy
Answers: 1
question
Business, 22.06.2019 12:00
In mexico, many garment or sewing shops found they could entice many young people to work for them if they offered clean, air conditioned work areas with high-quality locker rooms to clean up in after the work day. typically, traditional garment shops had to offer to get workers to apply for the hard, repetitive, and somewhat dangerous work. a. benchmark competitive wages b.compensating differentials c. monopoly wages d. wages based on human capital development of each employee
Answers: 3
question
Business, 22.06.2019 17:00
Which represents a surplus in the market? a market price equals equilibrium price. b quantity supplied is greater than quantity demanded. c market price is less than equilibrium price. d quantity supplied equals quantity demanded.
Answers: 2
You know the right answer?
Martinez Construction Company has entered into a contract beginning January 1, 2020, to build a park...
Questions
question
Mathematics, 26.06.2020 23:01
question
Mathematics, 26.06.2020 23:01
question
Mathematics, 26.06.2020 23:01