A project that provides annual cash flows of €28,500 for nine years costs €138,000 today. Requirement 1:
Is this a good project if the required return is 8 per cent?

No

Requirement 2:
Is this a good project if the required return is 20 per cent?

Yes

Requirement 3:
At what discount rate would you be indifferent between accepting the project and rejecting it?

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 19:00
James is an employee in the widget inspection department of xyz systems, a government contractor. james was part of a 3-person inspection team that found a particular batch of widgets did not meet the exacting requirements of the u.s. government. in order to meet the tight deadline and avoid penalties under the contract, james' boss demanded that the batch of widgets be sent in fulfillment of the government contract. when james found out, he went to the vice president of the company and reported the situation. james was demoted by his boss, and no longer works on government projects. james has a:
Answers: 3
question
Business, 22.06.2019 21:10
Acompany has two products: standard and deluxe. the company expects to produce 36,375 standard units and 62,240 deluxe units. it uses activity-based costing and has prepared the following analysis showing budgeted cost and cost driver activity for each of its three activity cost pools.budgeted activity of cost driver activity cost pool budgeted cost standard deluxe activity 1 $ 93,000 2,500 5,250 activity 2 $ 92,000 4,500 5,500 activity 3 $ 87,000 3,000 2,800 what is the overhead cost per unit for the standard units? what is the overhead cost per unit for the deluxe units? (round activity rate and cost per unit answers to 2 decimal places.)activity expected costs expected activity driver activity rate1 93,000 2 92,000 3 87,000 standard activity activity driver activity rate allocated costs1 2 3
Answers: 2
question
Business, 23.06.2019 00:10
Kcompany estimates that overhead costs for the next year will be $4,900,000 for indirect labor and $1,000,000 for factory utilities. the company uses direct labor hours as its overhead allocation base. if 100,000 direct labor hours are planned for this next year, what is the company's plantwide overhead rate?
Answers: 3
question
Business, 23.06.2019 05:50
Ineed the answer today! explain how inflation can be built into the system
Answers: 1
You know the right answer?
A project that provides annual cash flows of €28,500 for nine years costs €138,000 today. Requireme...
Questions