subject
Business, 13.01.2021 15:50 ohartshorn3670

The flowtime of the last job in a single work center’s schedule is 7 days. What is the makespan of this schedule?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 12:40
Alarge tank is filled to capacity with 500 gallons of pure water. brine containing 2 pounds of salt per gallon is pumped into the tank at a rate of 5 gal/min. the well-mixed solution is pumped out at the same rate. find the number a(t) of pounds of salt in the tank at time t.
Answers: 3
question
Business, 22.06.2019 22:50
Total marketing effort is a term used to describe the critical decision factors that affect demand: price, advertising, distribution, and product quality. define the variable x to represent total marketing effort. a typical model that is used to predict demand as a function of total marketing effort is based on the power function: d = axb suppose that a is a positive number. different model forms result from varying the constant b. sketch the graphs of this model for b = 0, b = 1, 0< b< 1, b< 0, and b> 1. (we encourage you to use excel to do this.) what does each model tell you about the relationship between demand and marketing effort? what assumptions are implied? are they reasonable? how would you go about selecting the appropriate model?
Answers: 1
question
Business, 22.06.2019 23:30
Sally mitchell works as a manager at an environmental organization. she is currently working on a global warming project and decides which tasks related to creating awareness about the issue need to be done. in addition, she is also deciding which members of her team will work on engaging with the public and which will work on lobbying with the government. she is also assigning people as team members to ensure that tasks are undertaken on time. which of the following categories of functions is mitchell undertaking? envisioning organizing controlling planning
Answers: 1
question
Business, 23.06.2019 00:50
Mr. drucker uses a periodic review system to manage the inventory in his dry goods store. he likes to maintain 15 sacks of sugar on his shelves based on the annual demand figure of 225 sacks. it costs $2 to place an order for sugar and costs $1 to hold a sack in inventory for a year. mr. drucker checks inventory one day and notes that he is down to 9 sacks; how much should he order?
Answers: 1
You know the right answer?
The flowtime of the last job in a single work center’s schedule is 7 days. What is the makespan of...