A project begins in January 2014; it is to be completed in October 2016. The contract price is $3,900 and the estimated total cost of the project is $3,000. Additional data for the project is provided below: 2014 2015 2016
Costs Incurred To Date $300 $2,400 $4,200
Estimated cost to Complete 2,700 1,600
Estimated Total Cost $3,000 $4,000 $4,200

Percentage of completion [PC]= (Costs incurred to date)/(Estimated total cost)

Required:
Compute the gross profit/loss recognized for each year under the PC method.

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 16:30
The movement of an economy from one condition to another and back again
Answers: 2
question
Business, 22.06.2019 13:10
Lin corporation has a single product whose selling price is $136 per unit and whose variable expense is $68 per unit. the company’s monthly fixed expense is $32,400. required: 1. calculate the unit sales needed to attain a target profit of $5,000. (do not round intermediate calculations.) 2. calculate the dollar sales needed to attain a target profit of $8,400.
Answers: 3
question
Business, 23.06.2019 02:30
Suppose a starbucks tall latte cost $4.00 in the united states, 5.00 euros in the euro area and $2.50 australian dollars in australia. nominal exchange rates are .80 euros per dollar and 1.4 australian dollars per u.s. dollar. where does purchasing power parity hold? a. both the euro area and australia. b. neither the euro area or australia. c. the euro area but not australia. d. australia but not the euro area.
Answers: 1
question
Business, 23.06.2019 02:40
This year, druehl, inc., will produce 60 comma 000 hot water heaters at its plant in delaware, in order to meet expected global demand. to accomplish this, each laborer at the plant will work 200 hours per month. if the labor productivity at the plant is 0.25 hot water heaters per labor hour, how many laborers are employed at the plant? number of laborers employed by the plant = nothing laborers (round your answer to the nearest whole number).
Answers: 2
You know the right answer?
A project begins in January 2014; it is to be completed in October 2016. The contract price is $3,90...
Questions
question
Mathematics, 04.02.2021 05:40
question
Mathematics, 04.02.2021 05:40
question
Mathematics, 04.02.2021 05:40
question
Mathematics, 04.02.2021 05:40