We have a project (Cardinal), with these activities in days: Activity A with duration 4 and no precedents. Activity B with duration 15 and predecessor. A, Activity C with duration 9 and predecessor. A, Activity D with duration 2 and predecessor B, Activity E has duration 6 and predecessors B and C, Activity F has duration 4 and predecessor D, and Activity G has duration 15 and predecessors of E and F. Draw this to answer the following questions. How long is this project scheduled to take

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 19:50
Which of the following best describes the economic effect that results when the government increases interest rates and restricts the lending of money? a. borrowing money becomes more expensive and there is less investment in production. b. the economy grows as investments result in larger profits. c. government spending drives up prices because of greater competition for goods and services. d. consumers save more money and spend less buying goods and services.
Answers: 2
question
Business, 22.06.2019 12:10
The cost of the beginning work in process inventory was comprised of $3,000 of direct materials, $10,000 of direct labor, and $10,000 of factory overhead. costs incurred during the period were comprised of $15,000 of direct materials costs, and $100,000 of conversion costs. the equivalent units of production (eup) for the period were 9,000 for direct materials and 6,000 for conversion. the costs per eup were:
Answers: 3
question
Business, 22.06.2019 20:50
Happy foods and general grains both produce similar puffed rice breakfast cereals. for both companies, thecost of producing a box of cereal is 45 cents, and it is not possible for either company to lower their productioncosts any further. how can one company achieve a competitive advantage over the other?
Answers: 1
question
Business, 22.06.2019 21:30
The adjusted trial balance for china tea company at december 31, 2018, is presented below:
Answers: 1
You know the right answer?
We have a project (Cardinal), with these activities in days: Activity A with duration 4 and no prece...
Questions
question
Mathematics, 29.01.2020 06:53
question
Social Studies, 29.01.2020 06:53