A project activity has an earliest completion time of 5, an activity time of 3, and a latest completion time of 6. What is the slack time for the activity?

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 19:20
The following selected amounts are reported on the year-end unadjusted trial balance report for a company that uses the percent of sales method to determine its bad debts expense. accounts receivable $ 435,000 debit allowance for doubtful accounts 1,250 debit net sales 2,100,000 credit all sales are made on credit. based on past experience, the company estimates 1.0% of credit sales to be uncollectible. what adjusting entry should the company make at the end of the current year to record its estimated bad debts expense
Answers: 2
question
Business, 22.06.2019 04:30
Georgia's gross pay was 35,600 this year she is to pay a federal income tax of 16% how much should georgia pay in federal income ax this year
Answers: 1
question
Business, 23.06.2019 00:40
An upper-middle-class manager tends to have hostile relationship with the working-class employees in the firm because of his tendency to perceive himself as superior to them based on his class background. in this example, the manager exhibits: question 14 options: 1) class consciousness. 2) cultural awareness. 3) social mobility. 4) group orientation.
Answers: 3
question
Business, 23.06.2019 03:50
John is a journalist he went to a product demonstration for a new computer some of what he heard was informative while the rest was meant to persuade consumers to buy the product which two statements in the excerpt are persuasive rather than informative
Answers: 2
You know the right answer?
A project activity has an earliest completion time of 5, an activity time of 3, and a latest complet...
Questions
question
Mathematics, 03.12.2021 01:10
question
Health, 03.12.2021 01:10
question
Mathematics, 03.12.2021 01:10