The following jobs are waiting to be processed at the same machine center. Jobs are logged as they arrive: Job Due Date Duration (days)
A 314 5
B 315 3
C 313 8
D 312 16
E 325 40

All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275. Assume each job starts at the beginning of the day and finishes at the end of the day (a job that begins on day 275 and takes 8 days will finish on day 282, and the next job begins in the morning of day 283). Compute all times based on initiating work on day 275.

The average tardiness (job lateness) for the sequence developed using the FCFS rule = days

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 19:40
Banana computers has decided to procure processing chips required for its laptops from external suppliers instead of manufacturing them in their own facilities. how will this decision affect the firm? a. the firm will be protected against the principal-agent problem. b. the firm's administrative costs will be low because of necessary bureaucracy. c. the firm will have more flexibility in purchasing and comparing prices of goods and services. d. the firm will have high-powered incentives, such as hourly wages and salaries.
Answers: 3
question
Business, 22.06.2019 23:10
Amazon inc. does not currently pay a dividend. analysts expect amazon to commence paying annual dividends in three years. the first dividend is expected to be $2 per share. dividends are expected to grow from that point at an annual rate of 4% in perpetuity. investors expect a 12% return from the stock. what should the price of the stock be today?
Answers: 1
question
Business, 23.06.2019 06:30
What did surprise you in personalities
Answers: 1
question
Business, 23.06.2019 09:00
Matthew decides to buy expensive designer jeans. less expensive jeans are available, but the added cost of the designer brand is worth it to matthew most likely because
Answers: 1
You know the right answer?
The following jobs are waiting to be processed at the same machine center. Jobs are logged as they a...
Questions
question
Chemistry, 30.09.2019 04:50
question
Mathematics, 30.09.2019 04:50