What will happen to a project's schedule if there are resource overloads and the critical path is delayed? a. Nothing will happen to the project's schedule if the critical path is delayed.
b. The project's schedule will slip only if the float / slack period for the critical path activities is not enough to resolve the resource overload issue.
c. The project's schedule will slip only if the float/slack period for the noncritical activities is not enough to resolve the resource overload issue.
d. There is never a delay in the critical path, because it is the longest path through the network.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 22:00
How would you cite different books by the same author on the works cited page? a. moore, jack h. folk songs and ballads. salem: poetry press, 1999. print. moore, jack h. ballads in poetry – a critical review. dallas: garden books, 1962. print. b. moore, jack h. folk songs and ballads. salem: poetry press, 1999. print. –––. ballads in poetry – a critical review. dallas: garden books, 1962. print. c. moore, jack h. ballads in poetry – a critical review. dallas: garden books, 1962. print. moore, jack h. folk songs and ballads. salem: poetry press, 1999. print. d. moore, jack h. ballads in poetry – a critical review. dallas: garden books, 1962. print. –––. folk songs and ballads. salem: poetry press, 1999. print.
Answers: 1
question
Business, 22.06.2019 10:00
Scenario: you have advised the owner of bond's gym that the best thing to do would be to raise the price of a monthly membership. the owner wants to know what may happen once this price increase goes into effect. what will most likely occur after the price of a monthly membership increases? check all that apply. current members will pay more per month. the quantity demanded for memberships will decrease. the number of available memberships will increase. the owner will make more money. bond's gym will receive more membership applications.
Answers: 1
question
Business, 23.06.2019 01:50
You are looking at a one-year loan of $16,500. the interest rate is quoted as 8.7 percent plus two points. a point on a loan is 1 percent (one percentage point) of the loan amount. quotes similar to this one are common with home mortgages. the interest rate quotation in this example requires the borrower to pay two points to the lender up front and repay the loan later with 8.7 percent interest. what rate would you actually be paying here?
Answers: 3
question
Business, 23.06.2019 07:40
If airlines do not change their prices how else might they try to compete with each other?
Answers: 3
You know the right answer?
What will happen to a project's schedule if there are resource overloads and the critical path is de...
Questions
question
English, 12.03.2021 21:40
question
Mathematics, 12.03.2021 21:40
question
Biology, 12.03.2021 21:40
question
Chemistry, 12.03.2021 21:40
question
Mathematics, 12.03.2021 21:40