Using the Guth text sections 12.1.1 to 12.1.1.7 explain which Plan Procurement Inputs you might use in your role as a newly assigned project manager. Why? How would you use them? Based on Guthâs text in Section 12.1.1 to 12.1.7 I would use the following Inputs in the Planning Process group of Procurement related activities-
1) Project Management Plan- This is needed because the project management plan will give idea about the list of the goods or services needed to be procured, it will give details about the acceptance criteria and it will also have the WBS (work breakdown structure) which can help in determining budget for each activity. The make or buy analysis will be a helpful tool.
2) Requirements Documents- This document has the details of the requirements of the project. This document details about the procurement activities and details about the various contract documents. The make or buy analysis can be a useful tool.
3) Risk Register- This includes the List of risks, Analysis of risks, and Risk response planning to manage procurement related risks.
4) Project Schedule- The project schedule contains the timelines for the various activities of the project and can be used to determine the required timelines for the services or goods to be procured.
5) Activity Resource Requirements- This document has all the details about resources required for the project, including people, materials and technology, etc.
6) Stakeholder Register- This document has all the details about the various stakeholders in the project. Stakeholders are important for procurement management.
7) OPA (Organizational Process Assets) â This document has the information of the organizationâs current procurement policies and these policies can be helpful in drafting a procurement management plan. This can also help in defining various contracts involved in procurement management.
Thus all of the above Inputs can significantly help to plan Procurement activities in order to generate outputs such as Procurement Management Plan, procurement Statement of Work, Procurement documents, Vendor/supplier source selection criteria and make-or-buy decisions.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 08:10
Exercise 15-7 crawford corporation incurred the following transactions. 1. purchased raw materials on account $53,000. 2. raw materials of $45,200 were requisitioned to the factory. an analysis of the materials requisition slips indicated that $9,400 was classified as indirect materials. 3. factory labor costs incurred were $65,400, of which $50,200 pertained to factory wages payable and $15,200 pertained to employer payroll taxes payable. 4. time tickets indicated that $55,000 was direct labor and $10,400 was indirect labor. 5. manufacturing overhead costs incurred on account were $81,700. 6. depreciation on the company’s office building was $8,100. 7. manufacturing overhead was applied at the rate of 160% of direct labor cost. 8. goods costing $89,400 were completed and transferred to finished goods. 9. finished goods costing $76,000 to manufacture were sold on account for $105,100. journalize the transactions. (credit account titles are automatically indented when amount is entered. do not indent manually.) no. account titles and explanation debit credit (1) (2) (3) (4) (5) (6) (7) (8) (9) (to record the sale) (to record the cost of the sale) click if you would like to show work for this question: open show work
Answers: 1
question
Business, 22.06.2019 10:00
University car wash built a deluxe car wash across the street from campus. the new machines cost $219,000 including installation. the company estimates that the equipment will have a residual value of $19,500. university car wash also estimates it will use the machine for six years or about 12,500 total hours. actual use per year was as follows: year hours used 1 3,100 2 1,100 3 1,200 4 2,800 5 2,600 6 1,200 prepare a depreciation schedule for six years using the following methods: 1. straight-line. 2. double-declining-balance. 3. activity-based.
Answers: 1
question
Business, 22.06.2019 18:00
Bond j has a coupon rate of 6 percent and bond k has a coupon rate of 12 percent. both bonds have 14 years to maturity, make semiannual payments, and have a ytm of 9 percent. a. if interest rates suddenly rise by 2 percent, what is the percentage price change of these bonds?
Answers: 2
question
Business, 22.06.2019 20:00
Miller mfg. is analyzing a proposed project. the company expects to sell 14,300 units, plus or minus 3 percent. the expected variable cost per unit is $15 and the expected fixed cost is $35,000. the fixed and variable cost estimates are considered accurate within a plus or minus 3 percent range. the depreciation expense is $32,000. the tax rate is 34 percent. the sale price is estimated at $19 a unit, give or take 3 percent. what is the net income under the worst case scenario?
Answers: 2
You know the right answer?
Using the Guth text sections 12.1.1 to 12.1.1.7 explain which Plan Procurement Inputs you might use...
Questions
question
Mathematics, 01.04.2021 02:20
question
Arts, 01.04.2021 02:20