subject
Business, 09.11.2020 16:40 DjPeaceQueen

There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days. The standard deviation of the critical path is: A. 3.
B. 5.
C. 9.
D. 16.
E. 25.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:20
Jimmy owns an ice cream parlor. he designs a schedule for the different tasks the employees have to perform in order to prevent monotony at work. according to the schedule, if an employee makes waffle cones on a day, he serves ice creams the next day and clears the tables on the day after that. jimmy is using the approach at his ice cream parlor.
Answers: 2
question
Business, 22.06.2019 09:20
Which statement best explains the relationship between points a and b? a. consumption reaches its highest point, and then supply begins to fall. b. inflation reaches its highest point, and then the economy begins to expand. c. production reaches its highest point, and then the economy begins to contract. d. unemployment reaches its highest point, and then inflation begins to decrease.
Answers: 2
question
Business, 22.06.2019 10:30
6carla would like to buy a dress, a dresser for her bedroom, and a home theater system. she has one month's worth of living expenses in her emergency fund. carla decides to save for the home theater system. did carla make the right decision? why or why not? a. yes; her emergency fund is full and the other items will probably be less expensive. b. yes; she could save more for her emergency fund, but the home theater will be harder to save for. c. no; she should save more for her emergency fund because she has saved less than the recommended amount. d. no; she should have bought the dress and dresser first because she could afford them right away. reset next
Answers: 2
question
Business, 22.06.2019 11:10
Suppose that the firm cherryblossom has an orchard they are willing to sell today. the net annual returns to the orchard are expected to be $50,000 per year for the next 20 years. at the end of 20 years, it is expected the land will sell for $30,000. calculate the market value of the orchard if the market rate of return on comparable investments is 16%.
Answers: 1
You know the right answer?
There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2...
Questions
question
Mathematics, 03.06.2021 16:40
question
Chemistry, 03.06.2021 16:40
question
Mathematics, 03.06.2021 16:40
question
Mathematics, 03.06.2021 16:40
question
Mathematics, 03.06.2021 16:40
question
Mathematics, 03.06.2021 16:40