Mike, a project team member indicates that his programming task will take about 5 days to complete if everything goes flawlessly. Normally, this type of task takes about 7 days. But, if things go wrong, it could take up to 8 days. What is his PERT duration

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 14:00
Which of the following would be an accurate statement about achieving a balanced budget
Answers: 1
question
Business, 22.06.2019 19:20
Win goods inc. is a large multinational conglomerate. as a single business unit, the company's stock price is estimated to be $200. however, by adding the actual market stock prices of each of its individual business units, the stock price of the company as one unit would be $300. what is win goods experiencing in this scenario? a. diversification discount b. learning-curveeffects c. experience-curveeffects d. economies of scale
Answers: 1
question
Business, 22.06.2019 20:00
What is the difference between total utility and marginal utility? a. marginal utility is subject to the law of diminishing marginal utility while total utility is not. b. total utility represents the consumer optimum while marginal utility gives the total utility per dollar spent on the last unit. c. total utility is the total amount of satisfaction derived from consuming a certain amount of a good while marginal utility is the additional satisfaction gained from consuming an additional unit of the good. d. marginal utility represents the consumer optimum while total utility gives the total utility per dollar spent on the last unit.
Answers: 3
question
Business, 22.06.2019 23:20
Nnette henri is paid an hourly wage of $8.90 for a 32-hour workweek of 4 days, 8 hours daily. for any work on the fifth day and on saturdays, she is paid one and one-half times her regular hourly rate. during a certain week, in addition to her regular 32 hours, henri worked 6 hours on the fifth day and 5 hours on saturday. for this workweek, henri’s total earnings are:
Answers: 1
You know the right answer?
Mike, a project team member indicates that his programming task will take about 5 days to complete i...
Questions