Consider the following tasks, times, and predecessors for an assembly of set-top cable converter boxes: TASK ELEMENT TIME (MINUTES) ELEMENT PREDECESSOR
A 1 โ€”
B 1 A
C 2 B
D 1 B
E 3 C, D
F 1 A
G 1 F
H 2 G
I 1 E, H
Given a cycle time of four minutes, develop an assembly line layout. Use the longest task time rule and the largest number of following tasks as a secondary criterion. What is the efficiency of your layout, assuming the 4-minute cycle time?Use the longest task time as primary criterion with largest number of following tasks as secondary criterion. (Round your answer to the nearest whole percent.) Efficiency

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 16:30
Who got instagram! ? if you do give it to me
Answers: 1
question
Business, 22.06.2019 22:40
When immigration adds to the size of the domestic labor pool, which of the following is likely to occur? a. wages decrease. b. productivity increases. c. consumption decreases. d. minimum wage increases.
Answers: 1
question
Business, 23.06.2019 02:30
Suppose a starbucks tall latte cost $4.00 in the united states, 5.00 euros in the euro area and $2.50 australian dollars in australia. nominal exchange rates are .80 euros per dollar and 1.4 australian dollars per u.s. dollar. where does purchasing power parity hold? a. both the euro area and australia. b. neither the euro area or australia. c. the euro area but not australia. d. australia but not the euro area.
Answers: 1
question
Business, 23.06.2019 05:30
What type of stock does a large company issue?
Answers: 3
You know the right answer?
Consider the following tasks, times, and predecessors for an assembly of set-top cable converter box...
Questions
question
Mathematics, 11.04.2020 17:02
question
Mathematics, 11.04.2020 17:12