Your team has been asked to test and document enhancements to a web application that allows buyers to purchase custom-printed canvas shoes. The tasks and dependencies are as follows: a. Create a testing plan Once the testing plan is ready, your team can:
b. Test the user interfaces
c. Test the database
d. Test the network
e. Write the documentation first draft When the user interface tests are complete, you can:
f. Perform user testing—enlist some users to test the user interface When the database and network testing are complete, you can:
g. Perform integration testing—network with the database When the user testing of the user interface and the database testing are complete, you can:
h. Perform integration testing—database, network, and user interface When all integration testing and user testing are complete, you can:
i. Perform system testing Then you can:
j. Review and revise documentation After all other tasks are complete, you can:
k. Obtain management approval
Duration estimates for the tasks: a. 3 days b. 10 days c. 6 days d. 7 days e. 20 days f. 5 days g. 3 days h. 2 days i. 8 days j. 4 days k. 5 days
1. Submit answers to the following questions in a SINGLE document. Put Microsoft Project screen shots in the document and submit the .mpp file. Documents without screen shots will receive zero points.
a) Create a network diagram and a Gantt chart for the project tasks using Microsoft Project.
What is the planned duration for the testing project?
What is the critical path for the testing project?
For each task NOT on the critical path, calculate the amount of slack available.
If the user testing of the user interface takes 15 days, what will the impact be on the project duration?
b) Go online and find at least two sites with definitions of fast tracking and crashing a project schedule.
Prepare proper reference citations for the sites you located, using APA style.
In your own words, write definitions for project fast tracking and project crashing.
Consider the plan you prepared for the software system testing project in the question above. If you were informed by management that you must reduce the planned duration of the project by five days, describe how you, as a project manager, could crash or fast track this project. Be specific in identifying exactly what could be changed in the project plan for each option.
If the request to speed up the project occurs after day 25 of the original schedule, what is the only option available?
c) Go online and research the difference between total slack and free slack.
Prepare proper reference citations for the sites you located, using APA style.
Write definitions of total slack and free slack in your own words.
Why would the distinction between different forms of slack be important to a project manager?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 20:30
Northington, inc. is preparing the company's statement of cash flows for the fiscal year just ended. using the following information, determine the amount of cash flows from operating activities using the indirect method: net income$182,000gain on the sale of equipment12,300proceeds from the sale of equipment92,300depreciation expense—equipment50,000payment of bonds at maturity100,000purchase of land200,000issuance of common stock300,000increase in merchandise inventory35,400decrease in accounts receivable28,800increase in accounts payable23,700payment of cash dividends32,000 $189,400.$332,200.$236,800.$261,400.$186,800.
Answers: 2
question
Business, 22.06.2019 00:00
Choose the list of the best uses for word processing software. lists, resumes, writing a book, and payroll data letters to your friends, resumes, spreadsheets, and school papers resumes, cover letters, databases, and crossword puzzles book reports, letters to your friends, resumes, and contracts
Answers: 2
question
Business, 22.06.2019 04:30
Required prepare the necessary adjusting entries in the general journal as of december 31, assuming the following: on september 1, the company entered into a prepaid equipment maintenance contract. birch company paid $3,400 to cover maintenance service for six months, beginning september 1. the payment was debited to prepaid maintenance. supplies on hand at december 31 are $3,900. unearned commission fees at december 31 are $7,000. commission fees earned but not yet billed at december 31 are $3,500. (note: debit fees receivable.) birch company's lease calls for rent of $1,600 per month payable on the first of each month, plus an annual amount equal to 1% of annual commissions earned. this additional rent is payable on january 10 of the following year. (note: be sure to use the adjusted amount of commissions earned in computing the additional rent.)
Answers: 1
question
Business, 22.06.2019 20:20
Tl & co. is following a related-linked diversification strategy, and soar inc. is following a related-constrained diversification strategy. how do the two firms differ from each other? a. soar inc. generates 70 percent of its revenues from its primary business, while tl & co. generates only 10 percent of its revenues from its primary business. b. soar inc. pursues a backward diversification strategy, while tl & co. pursues a forward diversification strategy. c. tl & co. will share fewer common competencies and resources between its various businesses when compared to soar inc. d. tl & co. pursues a differentiation strategy, and soar inc. pursues a cost-leadership strategy, to gain a competitive advantage.
Answers: 3
You know the right answer?
Your team has been asked to test and document enhancements to a web application that allows buyers t...
Questions
question
Mathematics, 17.12.2021 07:10
question
Physics, 17.12.2021 07:20