A project has an initial cost of $44,000. Expected cash flows as a result of this project are projected as indicated below. Calculate the payback period for this project. Assume a discount rate of 9%. Project X t Cash Flows
0 -44,000
1 10,000
2 10,000
3 15,000
4 18,000
5 15,000
Rate %: 9

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 07:20
Go follow my instagram atx_humberto
Answers: 2
question
Business, 22.06.2019 10:30
Jack manufacturing company had beginning work in process inventory of $8,000. during the period, jack transferred $34,000 of raw materials to work in process. labor costs amounted to $41,000 and overhead amounted to $36,000. if the ending balance in work in process inventory was $12,000, what was the amount transferred to finished goods inventory?
Answers: 2
question
Business, 22.06.2019 12:00
Describe the three different ways the argument section of a cover letter can be formatted
Answers: 1
question
Business, 22.06.2019 13:30
After successfully completing your corporate finance class, you feel the next challenge ahead is to serve on the board of directors of schenkel enterprises. unfortunately, you will be the only person voting for you. the company has 375,000 shares outstanding, and the stock currently sells for $40, if there are four seats in the current election, how much will it cost you to buy a seat?
Answers: 2
You know the right answer?
A project has an initial cost of $44,000. Expected cash flows as a result of this project are projec...
Questions
question
Mathematics, 09.04.2020 04:57
question
Law, 09.04.2020 04:57