5. Negative float can be attributed to (check all answers that apply): a. Duration of an activity(s) on the critical path or a near-critical path took more time than planned. b. An activity was added to the critical path or a near-critical path. c. The contractor used an "As Late As Possible" constraint. d. Budget overrun in critical activity(s).

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 10:00
What is the difference between an "i" statement and a "you" statement? a. the "i" statement is non-confrontational b. the "you" statement is non-confrontational c. the "i" statement is argumentative d. the "you" statement is neutral in tone select the best answer from the choices provided
Answers: 1
question
Business, 22.06.2019 13:40
Salge inc. bases its manufacturing overhead budget on budgeted direct labor-hours. the variable overhead rate is $8.10 per direct labor-hour. the company's budgeted fixed manufacturing overhead is $74,730 per month, which includes depreciation of $20,670. all other fixed manufacturing overhead costs represent current cash flows. the direct labor budget indicates that 5,300 direct labor-hours will be required in september. the company recomputes its predetermined overhead rate every month. the predetermined overhead rate for september should be:
Answers: 3
question
Business, 22.06.2019 20:00
How many organs are supplied at a zero price? (b) how many people die in the government-regulated economy where the government-set price ceiling is p = 0? the quantity qd – qa. the quantity qe – qa. the quantity qd – qe. (c) how many people die in the market-driven economy?
Answers: 1
question
Business, 22.06.2019 20:30
The smelting department of kiner company has the following production and cost data for november. production: beginning work in process 3,700 units that are 100% complete as to materials and 23% complete as to conversion costs; units transferred out 10,500 units; and ending work in process 8,100 units that are 100% complete as to materials and 41% complete as to conversion costs. compute the equivalent units of production for (a) materials and (b) conversion costs for the month of november.
Answers: 3
You know the right answer?
5. Negative float can be attributed to (check all answers that apply): a. Duration of an activity(s)...
Questions
question
Mathematics, 23.11.2019 07:31
question
Biology, 23.11.2019 07:31