Assume that task J has a most likely duration of 20 days, an optimistic duration of 13 days, and a pessimistic duration of 30 days. If the optimistic and pessimistic durations are 95 percent estimates, the standard deviation for task J is days. a) 5.167b) 5c) 4.67d) 3.2

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 15:20
Garfield corporation is considering building a new plant in canada. it predicts sales at the new plant to be 50,000 units at $5.00/unit. below is a listing of estimated expenses. category total annual expenses % of annual expense that are fixed materials $50,000 10% labor $90,000 20% overhead $40,000 30% marketing/admin $20,000 50% a canadian firm was contracted to sell the product and will receive a commission of 10% of the sales price. no u.s. home office expenses will be allocated to the new facility. the contribution margin ratio for garfield corporation is
Answers: 2
question
Business, 23.06.2019 00:00
What is a uniform law adopted by all states that facilitates business transactions?
Answers: 1
question
Business, 23.06.2019 02:20
Which one of the following is not a typical current liability? a. interest payable b. current maturities of long-term debt c. salaries payable d. mortgages payable
Answers: 3
question
Business, 23.06.2019 03:20
Draw, label and explain the circular flow model (cfm). include the following: firms, households, product market, and factor (or resource) market.who owns the productive resources? what are those resources? what payment does each type of resource earn? explain the two markets in the cfm and explain the roles that firms and household each play in the cfm.
Answers: 2
You know the right answer?
Assume that task J has a most likely duration of 20 days, an optimistic duration of 13 days, and a p...
Questions