On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 09:40
Salt corporation's contribution margin ratio is 78% and its fixed monthly expenses are $30,000. assume that the company's sales for may are expected to be $89,000. required: estimate the company's net operating income for may, assuming that the fixed monthly expenses do not change.
Answers: 1
question
Business, 23.06.2019 01:50
The de mesa family will soon be occupying their newly renovated house. however, the bathroom measuring 10ft. by 16 ft. still needs to be covered by tiles. if the tile that they desire measures 2/5 ft by 2/5 ft., how many tiles will they need to cover the bathroom floor?
Answers: 3
question
Business, 23.06.2019 10:30
This pie chart shows a sample weekly budget. in this budget, how much money is going toward optional expenses? $70 $75 $10 $35
Answers: 1
question
Business, 23.06.2019 14:40
Interest rates are expressed as a percentage of
Answers: 1
You know the right answer?
On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560....
Questions
question
Mathematics, 03.07.2019 06:30
question
Mathematics, 03.07.2019 06:30
question
History, 03.07.2019 06:30
question
Mathematics, 03.07.2019 06:30
question
Geography, 03.07.2019 06:30
question
Chemistry, 03.07.2019 06:30