Avery Construction assembles residential houses. It uses aâ job-costing system with twoâ direct-cost categoriesâ (direct materials and directâ labor) and oneâ indirect-cost poolâ (assembly support). Directâ labor-hours is the allocation base for assembly support costs. In December 2016â, Avery budgets 2017 âassembly-support costs to be $ 8,000,000 and 2017 directâ labor-hours to be 160,000. At the end of 2017â, Avery is comparing the costs of several jobs that were started and completed in 2017. Laguna Model Mission Model
Construction period Feb-June 2017 May-0ct 2017
Direct material costs $106,550 $127,450
Direct labor costs $36,250 $41,130
Direct labor-hours 970 1,000

Direct materials and direct labor are paid for on a contract basis. The costs of each are known when direct materials are used or when direct labor-hours are worked. The 2017 actual assembly-support costs were $8,400,000, and the actual direct labor-hours were 200,000.

Required:

a. Compute the (a) budgeted indirect-cost rate and (b) actual indirect-cost rate. Why do they differ?
b. What are the job costs of the Laguna Model and the Mission Model using (a) normal costing and (b) actual costing?
c. Why might Atkinson Construction prefer normal costing over actual costing?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 17:50
Identify which of the twelve basic functions listed below fit the description given.
Answers: 1
question
Business, 22.06.2019 12:30
land, a building and equipment are acquired for a lump sum of $ 1,000,000. the market values of the land, building and equipment are $ 300,000, $ 800,000 and $ 300,000, respectively. what is the cost assigned to the equipment? (do not round any intermediary calculations, and round your final answer to the nearest dollar.)
Answers: 1
question
Business, 22.06.2019 21:10
You are the manager of a large crude-oil refinery. as part of the refining process, a certain heat exchanger (operated at high temperatures and with abrasive material flowing through it) must be replaced every year. the replacement and downtime cost in the first year is $165 comma 000. this cost is expected to increase due to inflation at a rate of 7% per year for six years (i.e. until the eoy 7), at which time this particular heat exchanger will no longer be needed. if the company's cost of capital is 15% per year, how much could you afford to spend for a higher quality heat exchanger so that these annual replacement and downtime costs could be eliminated?
Answers: 1
question
Business, 22.06.2019 23:40
Martha is one producer in the perfectly competitive jelly industry. last year, martha and all of her competitors found themselves earning economic profits. if there is free entry and exit, what do you expect to happen to the number of suppliers in the industry and the price of jelly? the number of suppliers will increase, and the price of jelly will fall. the number of suppliers will decrease, and the price of jelly will increase. the number of suppliers will increase, and the price of jelly will increase. the number of suppliers will decrease, and the price of jelly will fall.
Answers: 3
You know the right answer?
Avery Construction assembles residential houses. It uses aâ job-costing system with twoâ direct-cost...
Questions
question
Mathematics, 17.12.2019 21:31