The two processes that must occur before moving forward to planning the project are: a. Collect requirements and define scope
b. Train project manager and select project
c. Identify project deliverables and prepare scope statement
d. Identify stakeholders and develop project charter

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 14:00
What is the quantity demanded when the price floor is $0.75 in the market for public transportation? a. 75,000 b. 116,000 c. 0 (zero) d. 100,000 e. 86,000?
Answers: 3
question
Business, 22.06.2019 08:40
Mcdonald's fast-food restaurants have a well-designed training program for all new employees. each new employee is supposed to learn how to perform standardized tasks required to maintain mcdonald's service quality. due to labor shortages in some areas, new employees begin work as soon as they are hired and do not receive any off-the-job training. this nonconformity to standards creates
Answers: 2
question
Business, 22.06.2019 09:30
Cash flows during the first year of operations for the harman-kardon consulting company were as follows: cash collected from customers, $385,000; cash paid for rent, $49,000; cash paid to employees for services rendered during the year, $129,000; cash paid for utilities, $59,000. in addition, you determine that customers owed the company $69,000 at the end of the year and no bad debts were anticipated. also, the company owed the gas and electric company $2,900 at year-end, and the rent payment was for a two-year period.
Answers: 1
question
Business, 22.06.2019 11:30
Leon and sara are arguing over when the best time is to degrease soup. leon says that it's easiest to degrease soup when it's boiling. sara says it's easiest to degrease soup when it's cold. who is correct? a. neither leon nor sara is correct. b. leon is correct. c. both leon and sara are correct. d. sara is correct. student b   incorrect which following answer correct?
Answers: 1
You know the right answer?
The two processes that must occur before moving forward to planning the project are: a. Collect req...
Questions
question
Spanish, 19.10.2020 07:01
question
Engineering, 19.10.2020 07:01
question
Mathematics, 19.10.2020 07:01
question
English, 19.10.2020 07:01
question
Mathematics, 19.10.2020 07:01
question
History, 19.10.2020 07:01