You are a project manager for the construction of a 16-mile road. The work is uniformly distributed over 12 weeks. The total approved budget for this project is $600,000. At the end of the first 4 weeks of work, $125,000 has been spent and four miles of road have been completed. The Earned Value at the end of week 4 is: a. $125,000 b. $2,400,000 [$600,000 * 4 miles] c. $150,000 [$600,000 * (4 miles/16 miles)] d. $200,000 [$600,000 * (4 weeks/12 weeks)]

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 20:20
while setting up his new office, an attorney ordered thick, frieze carpets for the floor. however, the building inspector had him remove the expensive carpeting. the building inspector stated that according to federal regulations, the office must be wheelchair accessible as it is a public area. he further explained that since wheelchairs do not maneuver well in thick, frieze carpeting, the carpets had to be removed and be replaced with smooth-textured carpets that do not restrict wheelchair maneuverability. this scenario illustrates how a company is influenced by the component of its specific environment.
Answers: 2
question
Business, 22.06.2019 12:00
Select the correct answer. martha is a healer, a healthcare provider, and an experienced nurse. she wants to share her daily experiences, as well as her 12 years of work knowledge, with people who may be interested in health and healing. which mode of internet communication can martha use? a. wiki b. email c. message board d. chat e. blog
Answers: 2
question
Business, 22.06.2019 19:00
Gus needs to purée his soup while it's still in the pot. what is the best tool for him to use? a. potato masher b. immersion blender c. rotary mixer d. whisk
Answers: 2
question
Business, 22.06.2019 21:40
The following items could appear on a bank reconciliation: a. outstanding checks, $670. b. deposits in transit, $1,500. c. nsf check from customer, no. 548, for $175. d. bank collection of note receivable of $800, and interest of $80. e. interest earned on bank balance, $20. f. service charge, $10. g. the business credited cash for $200. the correct amount was $2,000. h. the bank incorrectly decreased the business's by $350 for a check written by another business. classify each item as (1) an addition to the book balance, (2) a subtraction from the book balance, (3) an addition to the bank balance, or (4) a subtraction from the bank balance.
Answers: 1
You know the right answer?
You are a project manager for the construction of a 16-mile road. The work is uniformly distributed...
Questions
question
Mathematics, 13.08.2020 08:01
question
Mathematics, 13.08.2020 08:01
question
Mathematics, 13.08.2020 08:01
question
Mathematics, 13.08.2020 08:01
question
Mathematics, 13.08.2020 08:01
question
Mathematics, 13.08.2020 08:01