Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and three of D. D is made of three units of E.

Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.

Seventy units OF Product Z are required in Period 10. (Assume that there is currently no inventory on hand of any of these items.)

Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates.

Period 1 2 3 4 5 6 7 8 9 10
Item Z
OH = 0
LT = 2
SS = 0
Q = L4L Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item A
OH = 0
LT = 1
SS = 0
Q = L4L Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item B
OH = 0
LT = 1
SS = 0
Q = L4L Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item C
OH = 0
LT = 1
SS = 0
Q = L4L Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item D
OH = 0
LT = 1
SS = 0
Q = L4L Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item E
OH = 0
LT = 3
SS = 0
Q = L4L Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:30
Which of the following statements regarding the learning curve and economies of scale is accurate? answers: just as diseconomies of scale are presumed to exist if a firm gets too large, there is a corresponding increase in costs in the learning-curve model as the cumulative volume of production grows.where diseconomies of scale are presumed to exist if a firm gets too large, there is no corresponding increase in costs in the learning-curve model as the cumulative volume of production grows.where diseconomies of scale are presumed to exist if a firm gets too small, there is no corresponding increase in costs in the learning-curve model as the cumulative volume of production grows.just as diseconomies of scale are presumed to exist if a firm gets too small, there is a corresponding increase in costs in the learning-curve model as the cumulative volume of production grows.
Answers: 1
question
Business, 22.06.2019 12:50
Performance bicycle company makes steel and titanium handle bars for bicycles. it requires approximately 1 hour of labor to make one handle bar of either type. during the most recent accounting period, barr company made 7,700 steel bars and 2,300 titanium bars. setup costs amounted to $35,000. one batch of each type of bar was run each month. if a single company-wide overhead rate based on direct labor hours is used to allocate overhead costs to the two products, the amount of setup cost assigned to the steel bars will be:
Answers: 2
question
Business, 22.06.2019 20:30
Considered alone, which of the following would increase a company's current ratio? a. an increase in net fixed assets.b. an increase in accrued liabilities.c. an increase in notes payable.d. an increase in accounts receivable.e. an increase in accounts payable.
Answers: 3
question
Business, 22.06.2019 23:00
You cannot make copies of media, even as a personal backup, without violating copyright. true
Answers: 3
You know the right answer?
Assume that Product Z is made of two units of A and four units of B. A is made of three units of C a...
Questions
question
Mathematics, 07.05.2021 08:10
question
Mathematics, 07.05.2021 08:10
question
Mathematics, 07.05.2021 08:10