The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,500 units per 40-hour workweek:
Task Performance Time (seconds) Predecessors
A 22 -
B 30 A
C 15 A
D 14 A
E 12 B, C
F 27 D, E
Required:
a) Given the demand, the cycle time for the production of the new train set = (round your response to one decimal place).
b) The theoretical minimum number of work stations is ? (round your response up to the next whole number)

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 16:00
Corey is trying to save money to buy a new tv. he invests $800 into an account paying 6.5% simple interest. for how long must he save if the tv costs $950? a. 2 years b. 3 years c. 4 years d. 5 years
Answers: 1
question
Business, 22.06.2019 05:50
Nichols inc. manufactures remote controls. currently the company uses a plantminuswide rate for allocating manufacturing overhead. the plant manager is considering switchingminusover to abc costing system and has asked the accounting department to identify the primary production activities and their cost drivers which are as follows: activities cost driver allocation rate material handling number of parts $5 per part assembly labor hours $20 per hour inspection time at inspection station $10 per minute the current traditional cost method allocates overhead based on direct manufacturing labor hours using a rate of $20 per labor hour. what are the indirect manufacturing costs per remote control assuming an method is used and a batch of 10 remote controls are produced? the batch requires 100 parts, 5 direct manufacturing labor hours, and 3 minutes of inspection time.
Answers: 2
question
Business, 22.06.2019 16:40
Job 456 was recently completed. the following data have been recorded on its job cost sheet: direct materials $ 2,418 direct labor-hours 74 labor-hours direct labor wage rate $ 13 per labor-hour machine-hours 137 machine-hours the corporation applies manufacturing overhead on the basis of machine-hours. the predetermined overhead rate is $14 per machine-hour. the total cost that would be recorded on the job cost sheet for job 456 would be: multiple choice $3,380 $5,298 $6,138 $2,622
Answers: 1
question
Business, 22.06.2019 19:00
When making broccoli cream soup, the broccoli and aromatics should be a. burned. b. simmered. c. puréed. d. sweated.
Answers: 2
You know the right answer?
The Action Toy Company has decided to manufacture a new train set, the production of which is broken...
Questions
question
Mathematics, 20.10.2021 14:30
question
Mathematics, 20.10.2021 14:30