You were hired by a small business as the project manager of a project involving a market analysis. This project will determine whether the company goes ahead with the large scale manufacturing of a brand new product. The activities of the project are described below, with their respective durations:

ID Description Duration (2 weeks) Predecessor
A Survey designed 2 None
B Pilot 1 A
C Data collection 3 A
D Data Processing 1 B, C
E Analyze survey Results 2 D
F Analyze market trends 3 D
G Demographics 2 E
H Report and Presentation 2 F, G

Draw a project network with this information.

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 16:00
Match each feature with the savings account type
Answers: 3
question
Business, 21.06.2019 21:30
What is the eventual effect on real gdp if the government increases its purchases of goods and services by $80,000? assume the marginal propensity to consume (mpc) is 0.75. $ what is the eventual effect on real gdp if the government, instead of changing its spending, increases transfers by $80,000? assume the mpc has not changed. $ an increase in government transfers or taxes, as opposed to an increase in government purchases of goods and services, will result in an identical eventual effect on real gdp. a smaller eventual effect on real gdp. a larger eventual effect on real gdp. no change to real gdp.
Answers: 3
question
Business, 22.06.2019 10:00
Your uncle is considering investing in a new company that will produce high quality stereo speakers. the sales price would be set at 1.5 times the variable cost per unit; the variable cost per unit is estimated to be $75.00; and fixed costs are estimated at $1,200,000. what sales volume would be required to break even, i.e., to have ebit = zero?
Answers: 1
question
Business, 22.06.2019 12:50
Required information problem 15-1a production costs computed and recorded; reports prepared lo c2, p1, p2, p3, p4 [the following information applies to the questions displayed below. marcelino co.'s march 31 inventory of raw materials is $84,000. raw materials purchases in april are $540,000, and factory payroll cost in april is $364,000. overhead costs incurred in april are: indirect materials, $59,000; indirect labor, $26,000; factory rent, $38,000; factory utilities, $19,000; and factory equipment depreciation, $58,000. the predetermined overhead rate is 50% of direct labor cost. job 306 is sold for $670,000 cash in april. costs of the three jobs worked on in april follow. job 306 job 307 job 308 balances on march 31 direct materials $30,000 $36,000 direct labor 25,000 14,000 applied overhead 12,500 7,000 costs during april direct materials 133,000 210,000 $100,000 direct labor 105,000 150,000 101,000 applied overhead ? ? ? status on april 30 finished (sold) finished in process (unsold) required: 1. determine the total of each production cost incurred for april (direct labor, direct materials, and applied overhead), and the total cost assigned to each job (including the balances from march 31). a-materials purchases (on credit). b-direct materials used in production. c-direct labor paid and assigned to work in process inventory. d-indirect labor paid and assigned to factory overhead. e-overhead costs applied to work in process inventory. f-actual overhead costs incurred, including indirect materials. (factory rent and utilities are paid in cash.) g-transfer of jobs 306 and 307 to finished goods inventory. h-cost of goods sold for job 306. i-revenue from the sale of job 306. j-assignment of any underapplied or overapplied overhead to the cost of goods sold account. (the amount is not material.) 2. prepare journal entries for the month of april to record the above transactions. 3. prepare a schedule of cost of goods manufactured. 4.1 compute gross profit for april. 4.2 show how to present the inventories on the april 30 balance sheet.
Answers: 3
You know the right answer?
You were hired by a small business as the project manager of a project involving a market analysis....
Questions
question
Mathematics, 25.09.2020 14:01
question
Chemistry, 25.09.2020 14:01
question
Geography, 25.09.2020 14:01
question
Physics, 25.09.2020 14:01