Business, 21.04.2020 01:16 bcifuentes

Mr. Beautiful, an organization that sells weight trainingsets, has an ordering cost of $45 for the BB-1 set (BB-1 stands for Body Beautiful Number 1). The carrying cost for BB-1 is $20 per set per year. To meet demand, Mr. Beautiful orders large quantities of BB-1 7 times a year. The stockout cost for BB-1 is estimated to be $45

per set. Over the past several years, Mr. Beautiful has observed the following demand during the lead time for BB-1: Demand During Lead Time Probability
Value 1 10 0.1
Value 2 30 0.2
Value 3 50 0.2
Value 4 70 0.2
Value 5 90 0.2
Value 6 110 0.1

The reorder point for BB-1 is 50 sets. What level of safety stock should be maintained forBB-1?
The optimal quantity of safety stock which minimizes expected total cost is nothing

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 23:00
James has set the goal of achieving all "a"s during this year of school.which term best describes this goal
Answers: 2
question
Business, 22.06.2019 19:10
Greenway industries is a major multinational conglomerate. its business units compete in a range of industries, including home appliances, pharmaceuticals, commercial real estate, and plastics manufacturing. although its largest business unit, which produces kitchen appliances, is among the most profitable in the industry, it generates only 35 percent of the company's revenues. which of the following is most likely true of greenway's stock price? a. it is valued at less than the sum of its individual business units. b. it is valued at greater than the sum of individual business units. c. it is valued at the exact sum of individual business units. d. it is consistently lower than the industry average.it is valued at greater than the sum of individual business units.
Answers: 1
question
Business, 22.06.2019 23:10
Tony prince is the project manager for the recreation and wellness intranet project. team members include you, a programmer/analyst and aspiring project manager; patrick, a network specialist; nancy, a business analyst; and bonnie, another programmer/analyst. other people are supporting the project from other departments, including yusaff from human resources and cassandra from finance. assume that these are the only people who can be assigned and charged to work on project activities. recall that your schedule and cost goals are to complete the project in six months for under $200,000.task 2identify at least eight milestones for the recreation and wellness intranet project. write a short paper describing each milestone using the smart criteria. discuss how determining these milestones might add activities or tasks to the gantt chart. remember that milestones normally have no duration, so you must have tasks that will lead to completing the milestone.
Answers: 3
question
Business, 23.06.2019 01:00
"consists of larger societal forces that affect how a company engages and serves its customers."
Answers: 1
You know the right answer?
Mr. Beautiful, an organization that sells weight trainingsets, has an ordering cost of $45 for the B...
Questions
question
Mathematics, 27.10.2020 18:00
question
Chemistry, 27.10.2020 18:00