Business, 14.04.2020 22:49 IHATEIXL

You are managing a project with a BAC of $100,000, EV of $50,000, PV of 60,000, and AC of $40,000. The project sponsor asks you about the efficiency of the use of financial resources in the project so far. How would you answer her question

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 14:00
Which of the following is not a characteristic of a weak economy? a. a low employment rateb. a high inflation ratec. a decreased gdpd. a high unemployment rate
Answers: 1
question
Business, 22.06.2019 18:00
What is the cause of smoky exhaust?
Answers: 1
question
Business, 22.06.2019 19:10
Below are the steps in the measurement process of external transactions. arrange them from first (1) to last (6). event step post transactions to the general ledger. assess whether the transaction results in a debit or credit to account balances. use source documents to identify accounts affected by an external transaction. analyze the impact of the transaction on the accounting equation. prepare a trial balance. record the transaction in a journal using debits and credits.
Answers: 3
question
Business, 22.06.2019 19:30
Quick calculate the roi dollar amount and percentage for these example investments. a. you invest $50 in a government bond that says you can redeem it a year later for $55. use the instructions in lesson 3 to calculate the roi dollar amount and percentage. (3.0 points) tip: subtract the initial investment from the total return to get the roi dollar amount. then divide the roi dollar amount by the initial investment, and multiply that number by 100 to get the percentage. b. you invest $200 in stocks and sell them one year later for $230. use the instructions in lesson 3 to calculate the roi dollar amount and percentage. (3.0 points) tip: subtract the initial investment from the total return to get the roi dollar amount. then divide the roi dollar amount by the initial investment, and multiply that number by 100 to get the percentage.
Answers: 2
You know the right answer?
You are managing a project with a BAC of $100,000, EV of $50,000, PV of 60,000, and AC of $40,000. T...
Questions
question
Mathematics, 29.07.2019 03:30