subject
Business, 06.04.2020 22:35 avahymowitz44

You are assigned to a project with an initial budget of $200,000 USD. Midway through the project, you review the schedule and costs. Based on your review, You should have spent $50,000 to date based on your initial plans and 100 days activities that were based on the schedule.

You have actually spent $60,000 to date and completed activities for 110 days of the scheduled baseline, which should have cost $45,000 based on your initial plans. Budget required for the remaining work to be completed is estimated at $150,000.

Answer the following

PV (Planned Value) =
AC (Actual Cost) =
EV (Earned Value)=
ETC (Estimate to Complete) =
CPI =
SPI =
CV =
SV =
VAC (Variance at Completion) =
EAC (Estimate at Completion) =
TCPI =

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 19:00
Spirula trading inc sublets a part of its offices building to jade inc. for a period of ten years . where will the company disclose this information?
Answers: 3
question
Business, 21.06.2019 20:20
Jimmy owns an ice cream parlor. he designs a schedule for the different tasks the employees have to perform in order to prevent monotony at work. according to the schedule, if an employee makes waffle cones on a day, he serves ice creams the next day and clears the tables on the day after that. jimmy is using the approach at his ice cream parlor.
Answers: 2
question
Business, 21.06.2019 23:30
Actual usage for the year by the marketing department was 70,000 copies and by the operations department was 330,000 copies. if a dual-rate cost-allocation method is used, what amount of copying facility costs will be budgeted for the operations department?
Answers: 2
question
Business, 22.06.2019 14:20
Frugala is when sylvestor puts $2,000 into 10-year state bonds and $3,000 into 5-year aaa-rated bonds in steady hand hardware, inc. he buys the four state bonds at a 5 percent interest rate and the three steady hand bonds at a 6.5 percent rate. sylvestor also buys $1,500 worth of blue chip stocks, and $800 worth of stock in a promising new sportswear company that reinvests its earnings in new growth. 1. (a) what is the maturity for each of the bond groups sylvestor buys? (b) the coupon rate? (c) the par value?
Answers: 3
You know the right answer?
You are assigned to a project with an initial budget of $200,000 USD. Midway through the project, yo...
Questions
question
Mathematics, 01.12.2021 01:00