Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion.

PV = $23,000EV = $20,000AC = $25,000BAC = $120,000What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 19:50
One investigating company tracked all credit card purchase during 2012 and measured two variables: (1) the type of credit card used (visa, mastercard, american express, or discover), and (2) the amount (in dollars) of each purchase. identify the level of each variable measured.
Answers: 1
question
Business, 22.06.2019 08:30
Match the items with the actions necessary to reconcile the bank statement.(there's not just one answer)1. interest credited in bank account2. fee charged by bank for returned check3. checks issued but not deposited4. deposits yet to be crediteda. add to bank statementb. deduct from bank statementc. add to personal statementd. deduct from personal statement
Answers: 2
question
Business, 22.06.2019 21:20
Which of the following best explains why large companies pay less for goods from wholesalers? a. large companies are able to pay for the goods they purchase in cash. b. large companies are able to increase the efficiency of wholesale production. c. large companies can buy all or most of a wholesaler's stock. d. large companies have better-paid employees who are better negotiators.
Answers: 2
question
Business, 22.06.2019 22:00
Only the united states has embassies. true or false
Answers: 2
You know the right answer?
Given the following information for a one-year project, answer the following questions. Recall that...
Questions
question
Mathematics, 18.03.2021 17:40
question
Mathematics, 18.03.2021 17:40
question
History, 18.03.2021 17:40