Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended:
Standard variable-overhead rate per hour: $7.50
Standard fixed-overhead rate per hour: $12.40
Planned activity during the period: 19,000 machine hours
Actual production: 12,200 finished units
Machine-hour standard: Two completed units per machine hour
Actual variable overhead: $153,180
Actual total overhead: $432,900
Actual machine hours worked: 22,200
Required:
1. Calculate the budgeted fixed overhead for the year.
2. Compute the variable-overhead spending variance.
3. Calculate the company’s fixed-overhead volume variance.
4-a. Did Maxwell spend more or less than anticipated for fixed overhead? How much?
4-b. What was the difference in actual and anticipated overhead?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 04:00
Which law would encourage more people to become homeowners but not encourage risky loans that could end in foreclosure? options: offering first time homebuyers tax-free accounts to save for down payments requiring all mortgages to be more affordable, interest-only loans outlawing home inspections and appraisals by mortgage companies limiting rent increases to less than 2% a year
Answers: 2
question
Business, 22.06.2019 09:30
When you hire an independent contractor you don't have to pay the contractors what
Answers: 3
question
Business, 22.06.2019 20:30
The research of robert siegler and eric jenkins on the development of the counting-on strategy is an example of design.
Answers: 3
question
Business, 22.06.2019 21:00
Describe what fixed costs and marginal costs mean to a company.
Answers: 1
You know the right answer?
Maxwell Company uses a standard cost accounting system and applies production overhead to products o...
Questions
question
Mathematics, 23.11.2020 19:50
question
Mathematics, 23.11.2020 19:50