Metal frames for kick scooters are manufactured in two steps: Stamping and assembly. Each frame is made up of three pieces: one unit of part A and two units of part B.

The parts are fabricated by a single stamping machine that requires a set up time of 90 minutes switching between two part types. Once the machine is set up, the activity time for parts, regardless of type, is 30 seconds each piece. Currently, the stamping machine rotates its production between one batch of 120 part A’s and 240 part B’s. Completed parts move only when the entire batch is produced.

At assembly, parts are assembled manually to form the finished products. The three parts and a number of small purchased components are required for each unit of final product. Each product requires 30 minutes of labor time to assemble. There are 12 workers in assembly. There is sufficient demand to sell every scooter the system can make.

At the current batch sizes, what is the process capacity in units per hour? Choose the answer below that is closest to the correct answer. A unit refers to a complete scooter frame (i. e. one part A and two parts B)

a. 1 unit/ hr
b. 5 units/ hr
c. 10 units/ hr
d. 20 units/ hr
e. 24 units/ hr
f. 30 units/ hr
g. 40 units/ hr

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 16:10
Baldwin has negotiated a new labor contract for the next round that will affect the cost for their product bold. labor costs will go from $7.91 to $8.41 per unit. in addition, their material costs have fallen from $13.66 to $12.66. assume all period costs as reported on baldwin's income statement remain the same. if baldwin were to pass on half the new costs of labor and half the savings in materials to customers by adjusting the price of their product, how many units of product bold would need to be sold next round to break even on the product?
Answers: 2
question
Business, 22.06.2019 02:40
Which critical success factor improves with reduced cycle time, better quality standards, and improved efficiency when an is is implemented?
Answers: 3
question
Business, 22.06.2019 07:10
mark, a civil engineer, entered into a contract with david. as per the contract, mark agreed to design and build a house for david for a specified fee. mark provided david with an estimation of the total cost and the contract was mutually agreed upon. however, during construction, when mark increased the price due to a miscalculation on his part, david refused to pay the amount. this scenario is an example of a mistake.
Answers: 1
question
Business, 22.06.2019 11:40
Zachary company produces commercial gardening equipment. since production is highly automated, the company allocates its overhead costs to product lines using activity-based costing. the costs and cost drivers associated with the four overhead activity cost pools follow: activities unit level batch level product level facility level cost $ 64,800 $ 27,730 $ 15,000 $ 154,000 cost driver 2,400 labor hrs. 47 setups percentage of use 11,000 units production of 780 sets of cutting shears, one of the company’s 20 products, took 240 labor hours and 7 setups and consumed 15 percent of the product-sustaining activities. required: (a) had the company used labor hours as a company wide allocation base, how much overhead would it have allocated to the cutting shears? (b) how much overhead is allocated to the cutting shears using activity-based costing? (c) compute the overhead cost per unit for cutting shears first using activity-based costing and then using direct labor hours for allocation if 780 units are produced. if direct product costs are $150 and the product is priced at 30 percent above cost for what price would the product sell under each allocation system? (d) assuming that activity-based costing provides a more accurate estimate of cost, indicate whether the cutting shears would be over- or underpriced if direct labor hours are used as an allocation base. explain how over-or undercosting can affect vaulker's profitability. (e) comment on the validity of using the allocated facility-level cost in the pricing decision. should other costs be considered in a cost- plus pricing decision? if so, which ones? what costs would you include if you were trying to decide whether to accept a special order?
Answers: 1
You know the right answer?
Metal frames for kick scooters are manufactured in two steps: Stamping and assembly. Each frame is m...
Questions
question
Mathematics, 27.08.2021 19:40